Tender Notice No. | Description of the Tender | Due date for submission of Tender | Download Tender Document |
---|---|---|---|
GEM/2024/B/5584226 | Providing Round the Clock Security Services for TIFR Hyderabad Campus | 25.11.2024 15:00 Hrs | |
TIFR/PD/CF24-122/241045 | Supply and Fabrication of MS works for Petawatt Facility in TIFR,Survey No. 36/P, Gopanpally (Village),Serilingampally (Mandal), Ranga Reddy Dist.,Hyderabad-500046. | 18.11.2024 13:00 Hrs | |
TIFR/PD/CA24-69/240898 | Enquiry letter for Supply of Horizontal, three zones, gradient, split tube furnace connected with turbomolecular pump for operation in vacuum and inert atmosphere with the attached specifications - 01No for Tata Institute of Fundamental Research, Hyderabad. | 13.11.2024 | |
TIFR/PD/CF24-109/240930 | Facade work for Nutrition Facility at Plot-B,TIFR,Survey No. 36/P, Gopanpally (Village),Serilingampally (Mandal), Ranga Reddy Dist.,Hyderabad-500046. | 22.10.2024 13:00 Hrs | |
TIFR/PD/CF24-102/240900 | Supply, Installation, Testing and commissioning of fire detection & alarm system, VESDA and total flooding clean agent IG 541 gas fire suppression system for Petawatt Laser Facility,TIFR,Survey No. 36/P, Gopanpally (Village),Serilingampally (Mandal), Ranga Reddy Dist.,Hyderabad-500046. | 21.10.2024 13:00 Hrs | |
TIFR/PD/CF24-99/240858 | Construction of Balance C-C Road at Plot-B,TIFR , Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 14.10.2024 13:00 Hrs | |
TIFR/PD/CA24-62/240827 | Supply, Installation and Commissioning of 50 TW Compressor Vacuum Chamber for TIFR, Hyderabad Petawatt Laser Lab for TIFR, Hyderabad | 23.10.2024 13:00 Hrs | |
TIFR/PD/GT/IC24-4/240695 | Supply, Installation and Commissioning of Triple Quadrupole (QQQ) Liquid Chromatography mass Spectrometry | 15.10.2024 13:00 Hrs | |
TIFR/PD/GT/IC24-5/240696 | Supply, Installation and Commissioning of Liquid Chromatography mass Spectrometry | 14.10.2024 13:00 Hrs | |
TIFR/PD/GT/CA24-04/24-25/M/04 | Supply, Installation and Commissioning of a 100G Omnipath Switch with Accessories for the existing Kohinoor HPC Cluster | 10.10.2024 13:00 Hrs | |
TIFR/PD/IC 24-6/240711 | Supply, Installation and commissioning of System for Quantum Control and Measurement for TIFR, Hyderabad. | 07.10.2024 | |
TIFR/PD/ CF24-78/240656 | Supply, Installation, Testing and Commissioning of External Electrical works and other related works for Petawatt Laser Lab, Plot-B, TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 12.09.2024 13:00 Hrs | |
TIFR/PD/CF24-72/240617 | Supply, Installation, Testing & Commissioning of Fire Alarm System and other related works for Hostels, Plot-B, TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 17.09.2024 13:00 Hrs | PDFCorrigendum–I |
TIFR/PD/CA24-49/240628 | Supply, Installation and Commissioning of XRF Experimenter's Kit with X-123 for TIFR, Hyderabad Petawatt Laser Lab for TIFR, Hyderabad | 11.09.2024 13:00 Hrs | |
TIFR/PD/CA24-50/240633 | Supply, Installation, Testing and commissioning of High side and Low side HVAC works for Animal Facility in Hanger-02, TIFR , Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 05.09.2024 13:00 Hrs | |
TIFR/PD/CM24-349/240482 | Supply of Electronic Module for TIFR Hyderabad , Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 20.08.2024 13:00 Hrs | PDFPre-bid clarification |
TIFR/PD/CA24-37/240479 | Supply, Installation, Testing and commissioning of HVAC High side and Low side works for Petawatt Laser Facility,TIFR , Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 19.08.2024 13:00 Hrs | |
TIFR/PD/CF24-66/240472 | Supply, Installation, Testing and Commissioning of cleanrooms for Petawatt Facility at TIFR, Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046 | 07.08.2024 13:00 Hrs | |
GEM/2024/B/5204504 | Supply, Installation and commissioning of AMD based High performance computing servers for TIFR Hyderabad | 12.08.2024 14:00 Hrs | |
TIFR/PD/GT/CA24-03/24-25/M/03 | Supply, Installation, and Commissioning of Electron Microscope for TIFR Hyderabad | 27.08.2024 13:00 Hrs | |
TIFR/PD/GT/CA23-07/23-24/M/07 | Global tender document forSupply, Installation and Commissioning of High Resolution Transmission Electron Microscope for TIFR Hyderabad | 13.02.2024 13:00 Hrs | PDF Corrigendum No.1 Technically shortlisted bidders |
TIFR/PD/CF24-17/240087 | Setting up of “500 KWp Grid-connected Rooftop Solar PV Power Plant under RESCO mode” at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 including Operation & Maintenance (O & M) of the project for a period of 25 (Twenty-five) years after operational acceptance”. Zoom link for Pre-Bid Meeting 24-07-2024 11.00 Hrs. | 09-08-2024 13.00 Hrs. | PDF Corrigendum No.1 |
TIFR/PD/CF24-60/240410 | Supply, Installation, Testing and commissioning of New clean room and related works for Laser lab in FReT-B,TIFR,Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist.,Hyderabad-500046 Zoom link for Pre-Bid Meeting 25-07-2024 14.00 Hrs. Corrigendum No.1 | 06-08-2024 13.00 Hrs. | PDF Cancellation of Tender |
TIFR/PD/CA24-34/240376 | Supply, Installation, Testing and commissioning of High side and Low side HVAC works for Animal Facility in Hanger-02, TIFR,Hyderabad Zoom link for Pre-Bid Meeting 25-07-2024 10.00 Hrs. Corrigendum No.1 | 06-08-2024 13.00 Hrs. | PDF Cancellation of Tender |
TIFR/PD/CA24-21/240180 | Supply of Self pressurized Liquid Nitrogen Cylinders for TIFR Hyderabad Zoom link for Pre-Bid Meeting 19-06-2024 11.00 Hrs.Pre-bid clarificationsTechnically shortlisted bidders | 04-07-2024 13.00 Hrs. | TIFR/PD/CF24-23/240147 | Supply, Installation, Testing and commissioning of Cleanrooms for petawatt facility at TIFR, Hyderabad. Zoom link for Pre-bid meeting 07-06-2024 at 11:30 Hrs.Corrigendum – I Minutes of the Pre-Bid Meeting | 17-06-2024 13:00 Hrs. | TIFR/PD/CF24-22/240146 | Supply, Installation, Testing and commissioning of Air Distribution works for Petawatt Laser Facility at TIFR, Hyderabad.Zoom link for Pre-bid meeting 31-05-2024 at 11:00 Hrs. | 10-06-2024 13:00 Hrs. |
TIFR/PD/CF24-17/240087 | Setting up of “500 KWp Grid-connected Rooftop Solar PV Power Plant under RESCO mode” at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 including Operation & Maintenance (O & M) of the project for a period of 25 (Twenty-five) years after operational acceptanceZoom link for Pre-bid meeting 28-05-2024 at 11:00 Hrs.Corrigendum-I | 20-06-2024 13.00 Hrs | |
TIFR/PD/CA24-7/240059 | Supply, Installation, and Commissioning of Optical Tables for TIFR HyderabadZoom link for Pre-bid meeting 29-05-2024 11.00 Hrs.Pre-Bid clarification detailsTechnically shortlisted bidders | 13-06-2024 13.00 Hrs | |
TIFR/PD/CA24-01/24-25/M/01 | Supply, Installation, and Commissioning of AMD Bergamo Architecture based 256 cores High-Performance Computing (HPC) servers for TIFR HyderabadZoom link for Pre-bid meeting 28-05-2024 12.00 Hrs.Corrigenum No-1 | 12-06-2024 13.00 Hrs. | |
TIFR/PD/CA24-6/240056 | Supply, Installation, and Commissioning of 50TW Experimental Dodecagon Vacuum Chamber for TIFR Petawatt Laser LabZoom link for Pre-bid meeting 28-05-2024 11.00 Hrs.Pre-Bid clarification details | 11-06-2024 13.00 Hrs. | |
TIFR/PD/CA24-02/24-25/M/02 | Supply, Installation, and Commissioning of High-Performance Computing (HPC) Cluster for TIFR HyderabadZoom link for Pre-bid meeting 22-05-2024 11.00 HrsPre-Bid clarificationsCorrigendum No.1Corrigendum No.2Corrigendum No.3 | 18-07-2024 13.00 Hrs | |
TIFR/PD/CA23-149/231695 | Supply, Installation, and Commissioning of Optical Tables for TIFR HyderabadZoom link for Pre-bid meeting 16-05-2024 11.00 HrsPre-bid clarification detailsTechnically Shortlisted bidders | 04-06-2024 13.00 Hrs. | |
TIFR/PD/CA23-167/231911 | Supply, Installation, Testing and commissioning of 80 KVA Stabilizer & 80 KVA Ultra Isolation Transformer for CNC Machine at SB-2, FReTB, TIFR, , Hyderabad.Zoom link for Pre-bid meeting 22.04.2024 at 11:00 Hrs. | 29.04.2024 13:00 Hrs. | |
TIFR/PD/IC24-01/240001 | The Enquiry for the Supply, Installation, and commissioning of 5mm probe for 300MHz Nanobay NMR Spectrometer for TIFR Hyderabad Zoom link for Pre-bid meeting 23-04-2024 at 12.00 Hrs.Pre-bid meeting ClarificationsTechnically shortlisted bidders list | 08.05.2024 13:00 Hrs | PDFCorrigendum No.1 |
TIFR/PD/23241573/IC23-16/231683/01 | The Enquiry for the Supply, Installation, and commissioning of Cryosystem for a single crystal X-ray diffractometer for TIFR HyderabadZoom link for Pre-bid meeting 23-04-2024 at 11.00 Hrs.Pre-bid meeting ClarificationsTechnically Shortlisted bidders list | 30.04.2024 13:00 Hrs | |
TIFR/PD/RC24-25/200002 | Rate Contract for the Gases and Cryoliquids for TIFR HyderabadZoom link for Pre-bid meeting 04-04-2024 at 11.00 Hrs.Pre-bid meeting Clarifications | 22.04.2024 13:00 Hrs | |
TIFR/PD/RC24-25/200001 | Rate Contract for the Supply of Laboratory Research Chemicals, Glassware/ Plastic ware, Biological reagents_Branded Items, Specialized Consumables for TIFR Hyderabad.Zoom link for Pre-bid meeting 03-04-2024 at 11.00 Hrs. | 18.04.2024 13:00 Hrs | |
TIFR/PD/GT/CA23-10/23-24/M/10 | The Global tender document for Supply, Installation and Commissioning of State of the art 900MHz NMR spectrometer to carry out solid and solution state high-resolution NMR experiments to TIFR Hyderabad (GTE Ref:TIFR/PD/GT/CA23-10/23-24/M/10) and Publish Date:02-03-2024 Pre-bid meeting 12-03-2024 at 11.00 Hrs. | 02.04.2024 13:00 Hrs. | |
TIFR/PD/IC23-16/231683 | The attachment for Single tender Enquiry for Supply, Installation and commissioning of Cryosystem for single crystal X-Ray Diffractometer for TIFR Hyderabad(Ref. TIFR/PD/IC23-16/231683) with a due date on 06-03-2024.Tender Cancellation | 06.03.2024 | |
TIFR/PD/CA23-137/231618 | Supply, Installation and Commissioning of Double Door Autoclave with 1500L capacity for TIFR Hyderabad” (Tender ref. no. TIFR/PD/CA23-137/231618) Date of publishing: 17-02-2024 Pre-bid meeting 23-02-2024 at 11.00 Hrs.Pre-bid meeting clarificationsTechnically shortlisted bidderslist | 12.03.2024 13:00 Hrs. | TIFR/PD/CA23-143/231658 | Supply, Installation, Testing and commissioning of Pre-Insulated Ducting and other related works and other related works for Petawatt Laser Facility at TIFR, Hyderabad.Pre-bid meeting 20.02.2024 at 11:00 Hrs. | 11.03.2024 13:00 Hrs. | PDFCorrigendum-I | TIFR/PD/CF23-199/231641 | Annual Maintenance Contract for Maintenance of Horticulture, Landscaping, Mowing of lawn/grass and related works at TIFR, Survey No. 36/P, Gopanapally (Village), Serilingampally (Mandal), RR Dist., Hyderabad-500046.Pre-bid meeting 19.02.2024 at 11:00 Hrs. | 27.02.2024 13:00 Hrs. | TIFR/PD/CA23-136/231612 | Supply, Installation, Testing and Commissioning of Air Handling Units for Petawatt Laser Facility at TIFR, Hyderabad.Pre-bid meeting 15.02.2024 at 11:00 Hrs. | 29.02.2024 13:00 Hrs. | TIFR/PD/CF23-198/231608 | Annual Maintenance Contract for Operation & Maintenance of water supply, sewage system and carpentry works on 24x7 Basis on all days at TIFR, Survey No. 36/P, Gopanapally (Village), Serilingampally (Mandal), RR Dist., Hyderabad-500046.Pre-bid meeting 12.02.2024 at 11:00 Hrs. | 29.02.2024 13:00 Hrs. | PDF Corrigendum-1 | TIFR/PD/CF23-185/231518 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical, Fire Safety and HVAC installations on 24 x 7 basis” on all days at TIFR, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046.Pre-bid meeting 09.02.2024 at 11:00 Hrs. | 26.02.2024 13:00 Hrs. | PDF Corrigendum-1 | TIFR/PD/GT/CA23-09/23-24/M/09 | The Global tender document ref. TIFR/PD/GT/CA23-09/23-24/M/09 for Supply, Installation and Commissioning of High Performance Liquid Chromatography (HPLC) System with UV Detector for TIFR Hyderabad.Pre-bid meeting 08-02-2024 at 11.00 Hrs.Pre bid meeting clarification | 05.03.2024 13:00 Hrs | TIFR/PD/TS/CF-23/1002 | Painting and Stamp concrete work for underpass at TIFR-Hyderabad. | 02.02.2024 13:00 Hrs | PDFCorrigendum-I |
TIFR/PD/CA23-08/23-24/M/08 | Supply, installation and commissioning of a 100 G Omnipath switch with accessories for the existing Kohinoor HPC cluster for TIFR Hyderabad | 06.02.2024 13:00 Hrs | TIFR/PD/GT/CA23-07/23-24/M/07 | Global tender document forSupply, Installation and Commissioning of High Resolution Transmission Electron Microscope for TIFR Hyderabad | 13.02.2024 13:00 Hrs | PDF Corrigendum No.1 | TIFR/PD/CA23-168/231364 | Annual Maintenance Contract for Operation & Maintenance of water supply, sewage systemand carpentry works on 24x7 Basis on all days at TIFR, Survey No. 36/P, Gopanapally(Village), Serilingampally (Mandal), RR Dist., Hyderabad-500046. | 16.01.2024 13:00 Hrs | PDFCorrigendum-I |
TIFR/PD/CA23-88/231022 | Design, manufacture, supply, erection, testing and commissioning of Passenger lift of capacity | 02.01.2023 13:00 Hrs | |
TIFR/PD/CA23-93/231061 | The tender enquiry ref: TIFR/PD/CA23-93/231061 dated 15-11-2023 for Supply, Installation and Commissioning of High resolution Flurorespirometry setup for TIFR Hyderabad | 27.11.2023 Hrs. | |
TIFR/PD/CF23-137/231073 | Supply, Installation, Testing and commissioning of Pre-Insulated Ducting and other related works for Petawatt Laser Facility at TIFR, Hyderabad | 23.11.2023 13:00 Hrs. | |
TIFR/PD/CA23-91/231054 | Supply, Installation, Testing and Commissioning of Air Handling Units for Petawatt Laser Facility at TIFR, Hyderabad. | 21.11.2023 13:00 Hrs. | |
TIFR/PD/CF23-132/231053 | Supply, Installation, Testing & Commissioning of cleanrooms for Petawatt Facility at TIFR, Hyderabad. | 21.11.2023 13:00 Hrs. | |
TIFR/PD/CF23-130/231051 | Supply, Installation, Testing and Commissioning of Internal Electrification works and other related works for Petawatt Laser Lab Ground Floor, Plot-B, TIFR, Hyderabad. | 21.11.2023 13:00 Hrs. | |
TIFR/PD/CF23-126/231026 | Construction of Additional Civil & Interior Work for Petawatt Building at Plot-B, TIFR-Hyderabad. | 23.11.2023 13:00 Hrs | |
TIFR/PD/GT/IC23-13/231029 | Supply, Installation and Commissioning of Biological Indicator reader: 24 well Extracelluar Flux Analyzer for TIFR Hyderabad (Ref. TIFR/PD/GT/IC23-13/231029) | 12-12-2023 | |
TIFR/PD/GT/CA23-05/23-24/ M/05 | Supply, Installation and Commissioning of Electron Microscope for TIFR Hyderabad (Ref. TIFR/PD/GT/CA23-05/23-24/ M/ 05) & Publish Date: 11-11-2023 | 12-12-2023 | PDFCorrigendum-1 |
TIFR/PD/CF23-124/231023 | Supply, Installation, Testing & Commissioning of Internal Electrification works and other related works for Nutrition Facility, Plot-B, TIFR,Hyderabad. | 17.11.2023 13:00 Hrs | |
TIFR/PD/CA23-88/231022 | Design, manufacture, supply, erection, testing and commissioning of Passenger lift of capacity | 17.11.2023 13:00 Hrs. | |
TIFR/PD/CF23-125/231024 | Supply, Installation, Testing & Commissioning of Fire Alarm System & Fire Fighting works and other related works for Nutrition Facility, Plot-B, TIFR, Hyderabad. | 17.11.2023 13:00 Hrs. | |
TIFR/PD/CA23-87/231014 | Supply, Installation, Testing and Commissioning of Air Conditioners and other related works for Nutrition Facility at TIFR, Hyderabad. | 16.11.2023 13:00 Hrs. | |
TIFR/PD/CF23-116/230997 | Construction of Roof Covering Shed for Beam Hall at Plot B, TIFR-Hyderabad. | 15.11.2023 13:00 Hrs | |
TIFR/PD/CF23-113/230957 | Construction of Civil Super Structure and interior for National Center for Nutrition and metabolism at Plot B, TIFR-Hyderabad. | 10.11.2023 13:00 Hrs | |
TIFR/PD/CF23-108/230934 | Construction of MS Structure for National Center for Nutrition and metabolism at Plot B, TIFR-Hyderabad. | 10.11.2023 13:00 Hrs | |
TIFR/PD/CF23-107/230933 | Construction of Sub Structure for National Center for Nutrition and metabolism at Plot B, TIFR-Hyderabad. | 10.11.2023 13:00 Hrs | |
TIFR/PD/CA23-04/23-24/M/04 | Supply, Installation and Commissioning of State of the art 900 MHz NMR Spectrometer to carry out solid and solution state high-resolution NMR experiments to TIFR Hyderabad,publish Date : 07-10-2023. | 30.10.2023 1PM | |
DCSEM/CQD/QSA/EOI/TIFR-H/23-24/NIT/23 dt.04.10.2023 | Expression of Interest (EOI) cum Pre-qualification (PQ) applications through e-tendering mode from reputed, qualified, experienced and financially sound Engineering construction agencies for “Construction of Academic cum Residential complex alongwith other infrastructural facilities for Tata Institute of Fundamental Research, Hyderabad (TIFR-H) at Hyderabad, Telangana, India-500019” | 30.10.2023 1PM | |
TIFR/PD/CA23-61/230787 | Supply, Installation and Commissioning of Multitarget Sputtering system for TIFR Hyderabad,Publish Date:28-09-2023 Pre-Bid Meeting 06.10.2023 11:30AM Hrs | 19.10.2023 1PM | |
TIFR/PD/CA23-60/230769 | Supply, Installation and Commissioning of Microspectroscopy system for TIFR Hyderabad,Publish Date:28-09-2023 Pre-Bid Meeting 06.10.2023 11:00 Hrs | 19.10.2023 1PM | |
TIFR/PD/CA23-68/230823 | Design, Manufacture, Supply, Erection, Testing and Commissioning of Passenger lift of capacity 408 kgs (6 persons) for (G+1) Building at TIFR, Plot-B, sURVEY nO. 36/p, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist, Hyderabad-500046 Dated: September 26, 2023. | 04.10.2023 | |
TIFR/PD/CF23-90/230814 | Construction of Lift Machine room at Petawatt G+1 Building in Plot-B, TIFR, Hyderabad dated Sep 26, 2023 | 04.10.2023 | |
TIFR/PD/CA23-54/230673 | Supply, Installation and Commissioning of 2-Channel Radio Frequency Signal Generator to TIFR Hyderabad. | 20.09.2023 13:00 Hrs | |
TIFR/PD/CA23-02/23-24/M/02 | Supply, Installation and Commissioning of Nvidia RTX A6000 based 8 GPU server to TIFR Hyderabad. | 20.09.2023 13:00 Hrs | |
TIFR/PD/CF23-48/230460 | Covering of AHU at Hanger-2, TIFR, Hyderabad.Pre-Bid Meeting 17.07.2023 at 11:30 Hrs | 20-07-2023 13:00 Hrs | |
TIFR/PD/CF23-47/230454 | Underpass R.C.C Work at Plot-C at TIFR, HyderabadPre-Bid Meeting 14.07.2023 at 11:00 Hrs | 18-07-2023 13:00 Hrs | |
TIFR/PD/CA23-32/230388 | Supply, Installation and Commissioning of Quantum cascade laser system for TIFR HyderabadPre-Bid Meeting 10.07.2023 at 11:00 Hrs | 25-07-2023 13:00 Hrs | |
TIFR/PD/CF23-40/230360 | Extension of Lab Space and Modification Works at Ground Floor at Hanger-1, TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 28.06.2023 at 11:00 Hrs | 03-07-2023 13:00 Hrs | |
TIFR/PD/CF23-30/230282 | Construction of Civil Works for Petawatt Beam hall at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 30.06.2023 at 11:00 Hrs (Venue - TIFR Hyderabad) | 14-07-2023 13:00 Hrs | |
TIFR/PD/GT/IC23-01/23-24/M/01 | Supply, Installation and Commissioning of Nvidia H100 80 GB GPU Based Server with NVLink Interconnect for TIFR HyderabadPre-Bid Meeting 15.06.2023 at 11:00 Hrs | 08-08-2023 13:00 Hrs | |
TIFR/PD/CF23-21/230207 | UPVC Window Work for Petawatt Building First Floor at TIFR, HyderabadPre-Bid Meeting 05.06.2023 at 12:00 Hrs | 08-06-2023 13:00 Hrs | |
TIFR/PD/CF23-20/230206 | Flooring and Painting Work for Petawatt Building First Floor at TIFR, HyderabadPre-Bid Meeting 05.06.2023 at 11:30 Hrs | 08-06-2023 13:00 Hrs | |
TIFR/PD/CF23-24/230219 | Puff Panel Work for Petawatt Building First Floor at TIFR, HyderabadPre-Bid Meeting 08.06.2023 at 12:30 Hrs | 15-06-2023 13:00 Hrs | |
TIFR/PD/GT/IC22-27/22-23/M/027 | Supply, Installation, and Commissioning of High Resolution Mass Spectrometer System for TIFR HyderabadPre-Bid Meeting 13.04.2023 at 11:00 Hrs | 04-05-2023 13:00 Hrs | PDF Tender Cancellation |
TIFR/PD/GT/IC22-26/22-23/M/026 | Supply, Installation and Commissioning of Epifluorescence UV Microscope for TIFR Hyderabad Pre-Bid Meeting 12.04.2023 at 12:30 Hrs | 03-05-2023 13:00 Hrs | |
TIFR/PD/CF22-195/222004 | External Facade Work for Petawatt Building at TIFR, Hyderabad.Pre-Bid Meeting 03.04.2023 at 11:30 Hrs | 11-04-2023 13:00 Hrs | |
TIFR/PD/CF22-204/222092 | Kota Stone Flooring work for Petawatt Building at TIFR, HyderabadPre-Bid Meeting 28.03.2023 at 11:30 Hrs | 05-04-2023 13:00 Hrs | |
TIFR/PD/GT/IC22-23/22-23/M/023 | Corrigendum No. 1 for Supply, Installation and Commissioning of Cryostat for TIFR Hyderabad. | 11-04-2023 13:00 Hrs | |
TIFR/PD/CA22-208/222053 | Supply, Installation, Testing, and Commissioning of Split Air Conditioning Units & Related Work for NMR Lab at Main Building, Dr. Ritesh Lab Hanger Building-1 & BMS Room at Hanger Building-2, Plot-B, TIFR, Hyderabad | 09-03-2023 13:00 Hrs | |
TIFR/PD/CF22-201/222062 | Landscaping Works for hostel block-III at PLot-B, TIFR, Hyderabad.Pre-Bid Meeting 06.03.2023 at 11:30 Hrs | 09-03-2023 13:00 Hrs. | |
TIFR/PD/CA22-25/22-23/M/025 | Supply, Installation and Commissioning of Vector Network Analyzer for TIFR HyderabadTechnically Qualified Bidders | 06-04-2023 13:00 Hrs. | |
TIFR/PD/CA22-24/22-23/M/024 | Supply, Installation and Commissioning of Turbo Molecular Pumps for UHV application for TIFR HyderabadTechnically Qualified Bidders | 05-04-2023 13:00 Hrs. | |
TIFR/PD/CF22-195/222004 | External Facade Work for Petawatt Building at TIFR, Hyderabad.Pre-Bid Meeting 08.03.2023 at 11:30 Hrs | 13-03-2023 13:00 Hrs. | |
TIFR/PD/GT/IC22-23/22-23/M/023 | Supply, Installation and Commissioning of Cryostat for TIFR HyderabadPre-Bid Meeting 02.03.2023 at 11:00 HrsTechnically Qualified Bidders | 23-03-2023 13:00 Hrs. | |
TIFR/PD/CF22-187/221897 | Construction of Lift Machine Room between Hangar Buildings in Plot-B, TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 20.02.2023 at 11:30 Hrs | 27-02-2023 13:00 Hrs. | |
TIFR/PD/CA22-188/221801 | Supply, Installation, Testing, and Commissioning of 40 KVA UPS and other related works for 1st and 2nd Floor Right Wing Labs in Main Building at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 17.02.2023 at 11:00 Hrs | 22-02-2023 13:00 Hrs. | |
TIFR/PD/CA22-21/22-23/M/021 | Corrigendum No 2 - Supply, Installation and Commissioning of Intel Compute HPC Servers to TIFR Hyderabad. | 14-02-2023 13:00 Hrs. | |
TIFR/PD/CF22-181/221812 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical, Fire Safety and HVAC installations on 24 x 7 basis” on all days at TIFR, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046.Pre-Bid Meeting 13.02.2023 at 11:00 Hrs | 20-02-2023 13:00 Hrs. | |
TIFR/PD/CF22-182/221822 | Miscellaneous Work of Hostel Block-III at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 10.02.2023 at 11:30 Hrs | 14-02-2023 13:00 Hrs. | |
TIFR/PD/ GT/CA22-22/22-23/M/022 | Supply, Installation and Commissioning of Inductively Coupled Plasma Optical Emission Spectrometer for TIFR Hyderabad. | 23-02-2023 13:00 Hrs. | |
TIFR/PD/CF22-169/221720 | Duct Covering work (Jali) for Hostel Block-III at TIFR, Hyderabad.Pre-Bid Meeting 24.01.2023 at 11:30 Hrs | 27-01-2023 13:00 Hrs. | |
TIFR/PD/CA22-173/221576 | Corrigendum No 1 - Supply, Installation and Commissioning of Optical Tables for TIFR Hyderabad. | 30-01-2023 13:00 Hrs. | |
TIFR/PD/CA22-21/22-23/M/021 | Corrigendum No 1 - Supply, Installation and Commissioning of Intel Compute HPC Servers to TIFR Hyderabad. | 08-02-2023 13:00 Hrs. | |
TIFR/PD/CF22-159/221670 | Puff Panel Partition, Ceiling & Allied Civil Work for Petawatt Ground floor at TIFR, Survey No. 36/P,Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046.Pre-Bid Meeting 19.01.2023 at 11:00 Hrs | 27-01-2023 13:00 Hrs. | |
TIFR/PD/CF22-160/221690 | Vibration Isolation work for Laser Hall Petawatt Building at TIFR, Plot-B, Survey No. 36/P,Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046Pre-Bid Meeting 19.01.2023 at 11:30 Hrs | 27-01-2023 13:00 Hrs. | |
TIFR/PD/CA22-21/22-23/M/021 | Supply, Installation and Commissioning of Intel Compute HPC Servers to TIFR Hyderabad.Pre-Bid Meeting 18.01.2023 at 11:00 HrsTechnically Qualified Bidders | 01-02-2023 13:00 Hrs. | |
TIFR/PD/CA22-173/221576 | Supply, Installation and Commissioning of Optical Tables for TIFR Hyderabad | 19-01-2023 13:00 Hrs. | |
TIFR/PD/CF22-149/221548 | Miscellaneous works (SS Railing) at Hostel Block-III, TIFR, Hyderabad.Pre-Bid Meeting 23.12.2022 at 12:00 Hrs | 28-12-2022 13:00 Hrs. | |
TIFR/PD/CF22-148/221547 | Miscellaneous works (V-Board/Decorative Cladding) at Hostel Block-III, TIFR, Hyderabad.Pre-Bid Meeting 23.12.2022 at 11:30 Hrs | 28-12-2022 13:00 Hrs. | |
TIFR/PD/CA22-170/221526 | Supply, Installation, Testing & Commissioning of 10000 class cleanroom for laser lab at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046.Pre-Bid Meeting 23.12.2022 at 11:00 Hrs | 02-01-2023 13:00 Hrs. | |
TIFR/PD/CA22-161/221479 | Supply, Installation, Testing and Commissioning of Cassette ACs and other related works for Petawatt Building Office space at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 19.12.2022 at 11:00 Hrs | 26-12-2022 13:00 Hrs. | |
TIFR/PD/CA22-19/22-23/M/019 | Supply, Installation and Commissioning of Smart Server Racks to TIFR Hyderabad. Prebid meeting - 01/12/2022 11:00 AM, Venue - TIFR Hyderabad | 15-12-2022 13:00 Hrs. | |
TIFR/PD/CA22-18/22-23/M/018 | Supply, Installation and Commissioning of Big Data Servers for TIFR Hyderabad. Pre-Bid Meeting 30-11-2022 11:00 Hrs | 14-12-2022 13:00 Hrs. | |
TIFR/PD/CF22-119/221244 | Supply, Installation, Testing and Commissioning of Firefighting system for Hanger Building-II, TIFR, HyderabadPre-Bid Meeting 09-11-2022 12:00 Hrs | 14-11-2022 13:00 Hrs. | |
TIFR/PD/CF22-115/221213 | Interior Furnishing & Amenities works for Petawatt Building, Plot-B, TIFR, Hyderabad.Pre-Bid Meeting 10-11-2022 11:30 Hrs | 15-11-2022 13:00 Hrs. | |
TIFR/PD/CF22-110/221192 | Supply, Installation, Testing & Commissioning of Internal Electrification works and other related works for Peta Watt Laser Lab, First Floor, Plot-B, TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046. Pre-Bid Meeting 31-10-2022 12:00 Hrs | 07-11-2022 13:00 Hrs. | |
TIFR/PD/GT/IC22-20/221188 | Supply, Installation and Commissioning of Reactive Ion Etching (RIE) System with Load Lock for TIFR Hyderabad Pre-bid Meeting: Nil | 04-01-2023 13:00 Hrs. | |
TIFR/PD/GT/CA22-15/22-23/M/015 | Corrigendum No.2 against Global Tender Ref. No. TIFR/PD/GT/CA22-15/22-23/M/015 dated 26-07-2022 for Supply, Installation and Commissioning of Quadrupole-Time of Flight Liquid Chromatography Mass Spectrometry/Mass Spectrometer System (Q-TOF LCMS/MS system) for TIFR Hyderabad | 27-10-2022 13:00 Hrs. | |
TIFR/PD/CA22-119/221019 | Corrigendum No.1 for Supply, Installation, Testing and Commissioning of HVAC System and other related works for 10000 Class clean room at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046> | 11-10-2022 13:00 Hrs. | |
TIFR/PD/CF22-104/220180 | Construction of Supporting Steel Structure for Placing overhead water tank and caged exhaust units at Hanger II, Building.Pre-Bid Meeting 07-10-2022 11:30 AM | 13-10-2022 13:00 Hrs. | |
TIFR/PD/CA22-119/221019 | Supply, Installation, Testing and Commissioning of HVAC System and other related works for 10000 Class clean room at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046Pre-Bid Meeting 03-10-2022 11:00 AM | 11-10-2022 13:00 Hrs. | |
TIFR/PD/GT/CA22-15/22-23/M/015 | Corrigendum No.1 against Global Tender Ref. No. TIFR/PD/GT/CA22-15/22-23/M/015 dated 26-07-2022 for Supply, Installation and Commissioning of Quadrupole-Time of Flight Liquid Chromatography Mass Spectrometry/Mass Spectrometer System (Q-TOF LCMS/MS system) for TIFR Hyderabad | 20-10-2022 13:00 Hrs. | |
TIFR/PD/CF22-96/220995 | Tender For Providing Catering & Serving Services for TIFR, Hyderabad | 13-10-2022 13:00 Hrs. | |
TIFR/PD/GT/CA22-17/22-23/M/017 | Supply, Installation and Commissioning of Inductively Coupled Plasma Optical Emission Spectrometer for TIFR, Hyderabad | 23-11-2022 13:00 Hrs. | |
TIFR/PD/CF22-85/220902 | Interior Furnishing & Amenities Works for Hostel Block-III at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 10-09-2022 11.30 AM | 22-09-2022 13:00 Hrs. | |
TIFR/PD/CF22-79/220871 | Supply, Installation, Testing & Commissioning of internal electrification works and other related works for HPC Data Center at SB-2, TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad- 500046Pre-Bid Meeting 05-09-2022 11.00 AM | 09-09-2022 13:00 Hrs. | |
TIFR/PD/CF22-81/220888 | Plumbing Works for Hostel Block-III at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046Pre-Bid Meeting 06-09-2022 03.30 PM | 15-09-2022 13:00 Hrs. | |
TIFR/PD/CF22-72/220794 | Annual Maintenance Contract for deploying Manpower for Plumbing | Carpentry Works | Operation & Maintenance of STP at TIFR, Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046.Pre-Bid Meeting 26-08-2022 11.00 AM | 01-09-2022 13:00 Hrs. | |
TIFR/PD/CF22-66/220701 | Comprehensive Annual Maintenance Contract for 4TR LLOYD Tower AC Units - 6 Nos installed at TIFR Hyderabad, Survey No.36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad-500046 | 23-08-2022 | |
TIFR/PD/GT/CA22-15/22-23/M/015 | |||
TIFR/PD/IC22-15/220676 | Supply, Installation and Commissioning of High-Resolution Respirometry Setup Instrument for TIFR Hyderabad | 24-08-2022 Up to 13:00 Hrs | |
TIFR/PD/GT/CA22-15/22-23/M/015 | Supply, Installation and Commissioning of Quadrupole-Time Of Flight Liquid Chromatography Mass Spectrometry/Mass Spectrometer System (Q-TOF LCMS/MS system) with dual ionization source for qualitative and quantitative metabolomics and lipidomics for TIFR Hyderabad Pre-bid Meeting : Nil | 28-09-2022 Up to 13:00 Hrs | |
TIFR/PD/GT/CA22-14/22-23/M/014 | Supply, Installation and Commissioning of Steady state and time-correlated single photon counting (TCSPC) fluorescence spectrometer for TIFR Hyderabad | 27-09-2022 Up to 13:00 Hrs | |
TIFR/PD/GT/CA22-13/22-23/M/013 | Supply ,Installation and Commissioning of Steady state fluorescence spectrometer for TIFR Hyderabad | 27-09-2022 Up to 13:00 Hrs | |
TIFR/PD/CA22-78/220614 | Supply, Installation and Commissioning of Optical Tables for TIFR Hyderabad | 10-08-2022 Up to 13:00 Hrs | |
"NIT No.DCSEM/CQD/QSA/TIFR-H/Consultancy/18 dt.08.02.2022 | Status of Bidders ie. Technical score, Financial score and Final score based on Quality-cum-Cost based Selection (QCBS) adopted for Selection of Consultant/Agency for Providing Comprehensive Consultancy Services for Setting up a State-of-the-Art Academic-cum-Residential Campus for the TATA Institute of Fundamental Research Hyderabad (TIFR-H) at Hyderabad, Telangana, India | 18-07-2022 Up to 13:00 Hrs | |
TIFR/PD/CA22-61/220492 | Corrigendum-I for Design, manufacture, supply, erection, testing, and commissioning of Passenger lift of capacity 408 kgs (6 persons) for (G+1) Building at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 | 18-07-2022 Up to 13:00 Hrs | |
TIFR/PD/CF22-51/220546 | Supply, Installation, Testing, and Commissioning of Internal Electrification and other related works for Hostel Block-III, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid on 15-07-2022, 11:00 Hrs | 22.07.2022 Up to 13:00 Hrs | |
TIFR/PD/CF22-45/220468 | Construction of Deck Sheeting and Concreting for Hostel Block-III at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid on 04-07-2022, 11:00 Hrs | 11-07-2022 by 13:00 Hrs | |
TIFR/PD/CF22-46/220469 | Construction of Civil Super Structure for Hostel Block-III at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid on 04-07-2022, 11:30 Hrs | 12-07-2022 by 13:00 Hrs | |
TIFR/PD/CA22-61/220492 | Design, manufacture, supply, erection, testing and commissioning of Passenger lift of capacity 408 kgs (6 persons) for (G+1) Building at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid on 04-07-2022, 11:00 Hrs | 11-07-2022 Up to 13:00 Hrs. | |
TIFR/PD/GT/IC22-02/M/002 | Corrigendum No 1 - Supply, Installation and Commissioning of 12T Cryogen-free Dilution Refrigerator with Bottom load-lock for TIFR Hyderabad | 28-06-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-42/220351 | Corrigendum-I for Supply, Installation, Testing, and Commissioning of 120 KVA modular(N+1) UPS with 15 mins backup and other related works for data center at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 | 27-06-2022 upto 13:00 Hrs | Corrigendum-IPDFPresentation |
TIFR/PD/CF22-23/220278 | Corrigendum-I for Design Consultancy for Design of Beam Hall Concrete Structure & Internal Lab at TIFR Hyderabad, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 | 22-06-2022 up to 13:00 Hrs | |
TIFR/ADM/CA22-52/220399 | Tender for the Supply, Installation, Testing & Commissioning of LPG pipeline with gas bank, exhaust hood with ducting work and other kitchen items to TIFR at Gopanpally, Hyderabad | 29-06-2022 up to 13:00 Hrs | |
TIFR/PD/GT/TS/CF-21/19021 | List of qualified agencies for the tender - Prequalification -EOI for Providing Comprehensive Consultancy Services for setting up a State of the art Academic cum Residential Campus for TIFR at Hyderabad, Telangana, India | ||
TIFR/ADM/CF22-33/220398 | TENDER FOR PROVIDING HOUSEKEEPING SERVICES FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD | 29-06-2022 up to 13:00 Hrs | |
TIFR/PD/CA22-40/220341 | Corrigendum No -1 Limited Tender Enquiry for Supply, Installation, Testing, and Commissioning of Air Conditioners and other related works for Dr. T.N. Narayanan's XPS Lab and Glovebox setup on the Ground Floor, Right Wing, FReTB, TIFR Hyderabad | 14-06-2022 | |
TIFR/PD/CA22-47/220359 | Limited Tender Enquiry for Supply, Installation, Testing, and Commissioning of Air Conditioners and other related works for Dr. Ritesh Haldar's Lab in Hanger Building-1 at Plot-B, TIFR Hyderabad | 15-06-2022 upto 13:00 Hrs | |
TIFR/PD/IC22-8/220352 | CORRIGENDUM NO. 1 Supply and Installation of Optical Tables for TIFR Hyderabad. | 05-07-2022 upto 13:00 Hrs | |
TIFR/PD/IC22-8/220352 | Supply and Installation of Optical Tables for TIFR Hyderabad. | 05-07-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-42/220351 | Supply, Installation, Testing, and Commissioning of 120 KVA modular(N+1) UPS with 15 mins backup and other related works for data center at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 Pre Bid on 13-06-2022, 11:00 Hrs | 20-06-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-40/220341 | Limited Tender Enquiry for Supply, Installation, Testing, and Commissioning of Air Conditioners and other related works for Dr. T.N. Narayanan's XPS Lab and Glovebox setup on the Ground Floor, Right Wing, FReTB, TIFR Hyderabad | 09-06-2022 upto 13:00 Hrs | |
TIFR/PD/CF22-23/220278 | Design Consultancy for Design of Beam Hall Concrete Structure & Internal Lab at TIFRHyderabad, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), RangaReddy Dist., Hyderabad-500046. Pre Bid on 07-06-2022, 11:00 Hrs | 15-06-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-05/22-23/M/005 | Corrigendum No.2 for Supply, installation and commissioning of High-Performance Computing (HPC) Cluster for TIFR Hyderabad | 15-06-2022 upto 13:00 Hrs | |
TIFR/PD/CF22-24/220282 | Construction of Parking Shed at TIFR Hyderabad, Plot-B, Survey No. 36/P, Gopanpally(Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid on 03-06-2022, 11:00 Hrs | 13-06-2022 Upto 13:00 Hrs | |
TIFR/PD/CF22-18/220246 | Construction of Civil Super Structure for Petawatt lab at TIFR Hyderabad, Plot-B, Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 Pre Bid on 31-05-2022, 11:00 Hrs | 08-06-2022 Upto 13:00 Hrs | |
TIFR/PD/CF22-16/220220 | Connecting Corridor Work between Hanger Building-1 & 2 at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 Pre Bid on 23-05-2022, 11:00 Hrs | 27-05-2022 Upto 13:00 Hrs | |
TIFR/PD/CA22-05/22-23/M/005 | Corrigendum No.1 for Supply, installation and commissioning of High-Performance Computing (HPC) Cluster for TIFR Hyderabad | 31-05-2022 upto 13:00 Hrs | |
TIFR/PD/CF22-3/220033 | Supply, Installation, Testing, and Commissioning of Building Management System (BMS) and other related works for Animal Facility in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 Pre Bid on 17-05-2022, 11:00 AM | 26-05-2022 Upto 13:00 Hrs | |
TIFR/PD/CA22-07/22-23/M/007 | Supply, Installation and Commissioning of additional compute node to Epstein Drive HPC Cluster for TIFR Hyderabad. | 07-06-2022 Upto 13:00 Hrs | |
TIFR/PD/CA22-06/22-23/M/006 | Supply, Installation and Commissioning of a Computer Controlled Automatic System for Gas & Vapor Adsorption Studies for TIFR Hyderabad. | 07-06-2022 Upto 13:00 Hrs | |
TIFR/PD/CF22-7/220111 | Construction of Sub Structure for Hostel Block-III at TIFR, Plot-B, TIFR Hyderabad, Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Rangareddy Dist. Hyderabad-500046 Pre Bid on 12-05-2022, 11:00 AM | 19-05-2022 Upto 13:00 Hrs | |
TIFR/PD/CF22-8/220112 | Construction of MS Structure for Hostel Block-III at TIFR, Plot-B, TIFR Hyderabad, Survey No.36/P, Gopanpally (Village), Serilingampallyl (Mandal), Rangareddy Dist. Hyderabad-500046 Pre Bid on 12-05-2022, 11:30 AM | 20-05-2022 Upto 13:00 Hrs | |
TIFR/PD/CA22-05/22-23/M/005 | Supply, installation and commissioning of High-Performance Computing (HPC) Cluster for TIFR Hyderabad | 19-05-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-01/22-23/M/001 | Supply, Installation and Commissioning of 5 Axes Universal Type CNC Machining Centre Along with Tools and Technology Used in The Development of Desired Components for TIFR Hyderabad | 18-05-2022 upto 13:00 Hrs | |
TIFR/PD/CA22-04/22-23/M/004 | Supply, installation and commissioning of Steady State fluorescence spectrometer for TIFR Hyderabad | 18-05-2022 upto 13:00 Hrs | |
TIFR/PD/CA21-40/21-22/210040 | Corrigendum No:2 Supply, Installation and Commissioning of GPU workstation based High performance Computing Cluster (HPCC) for TIFR Hyderabad | 27-04-2022 upto 13:00 hrs | |
TIFR/PD/GT/IC22-02/M/002 | Supply, Installation and Commissioning of 12T Cryogen-free Dilution Refrigerator with Bottom load-lock for TIFR Hyderabad Pre-bid Meeting: NIL | 21-06-2022 upto 13:00 Hrs | |
TIFR/PD/GT/IC22-1/220002 | Supply, Installation and Commissioning of State of the Art 900 MHz NMR Spectrometer to carry out solid and solution state NMR experiments for TIFR Hyderabad Pre-bid Meeting: NIL | 14-06-2022 upto 13:00 Hrs | |
TIFR/PD/CA21-39/21-22/210039 | Corrigendum No:1 Supply, Installation and Commissioning of additional compute node to Epstein Drive HPC Cluster for TIFR Hyderabad | 26-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-245/21-22/211755 | Corrigendum No:1 Supply, Installation, and Commissioning of 100G Infiniband/RoCE/RDMA Switch with accessories | 26-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-41/21-22/210041 | Corrigendum No:1 Supply, Installation and Commissioning of additional compute nodes to Golconda 2 HPC cluster for TIFR Hyderabad | 20-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-40/21-22/210040 | Corrigendum No:1 Supply, Installation and Commissioning of GPU workstation based High performance Computing Cluster (HPCC) for TIFR Hyderabad | 20-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-245/21-22/211755 | Supply, Installation and Commissioning of 100G Infinitiband/RoCE/RDMA Switch with accessories for TIFR Hyderabad | 11-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-40/21-22/210041 | Supply, Installation and Commissioning of additional compute nodes to Golconda 2 HPC Cluster for TIFR Hyderabad | 11-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-40/21-22/210040 | Supply, Installation and Commissioning of a GPU Workstation based High Performance computing Cluster (HPCC) for TIFR Hyderabad | 11-04-2022 upto 13:00 hrs | |
TIFR/PD/CA21-39/21-22/210039 | Supply, Installation and Commissioning of additional compute node to Epstein Drive HPC Cluster for TIFR Hyderabad | 11-04-2022 upto 13:00 hrs | |
TIFR/PD/CF21-157/211722 | Supply, Installation, Testing, and Commissioning of Street Lights and other related works at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 Pre Bid Meeting on Mar 9, 2022 - 11:00 Hrs | 14-03-2022 upto 13:00 hrs | |
TIFR/PD/CF21-156/211698 | Landscaping Works for Hostel Block-II at Plot-B, TIFR Hyderabad at Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Rangareddy Dist, Hyderabad-500046. Pre Bid Meeting on Mar 4, 2022 - 11:00 Hrs | 08-03-2022 upto 13:00 hrs | |
TIFR/PD/IC21-29/21-22/210029 | CORRIGENDUM NO. 1, against Tender Ref. No. TIFR/PD/IC21-29/21-22/210029 dated 11-02-2022 for Supply, Installation and Commissioning of Atomic Force Microscope (AFM) for TIFRHyderabad. | 14-03-2022 upto 13:00 hrs | |
TIFR/PD/CA21-185/21-22/211316 | Supply, Installation and Commissioning of Big Data Servers for TIFR Hyderabad. | 15-03-2022 upto 13:00 hrs | |
TIFR/PD/IC21-29/21-22/210029 | Supply, Installation and Commissioning of Atomic Force Microscope (AFM) for TIFR Hyderabad. | 14-03-2022 upto 13:00 hrs | |
TIFR/PD/IC21-28/21-22/210028 | Supply, Installation and Commissioning of RIE System with Load Lock for TIFR Hyderabad. | 14-03-2022 upto 13:00 hrs | |
TIFR/PD/CF21-135/211552 | Annual Maintenance Contract for Engaging of Two Unskilled Gardeners for Maintenance of Horticulture, Landscaping, and related works at TIFR, FReTB, Survey No.36/P, Gopanpally (Village), Serilingampally (Mandal), Rangareddy Dist, Hyderabad-500046. Pre Bid Meeting on Feb 11, 2022 - 11:00 Hrs | 16-02-2022 upto 13:00 hrs | |
TIFR/PD/CF21-134/211521 | Corrigendum – I : Construction of MS Structure for Petawatt Building at Plot-B, TIFR, Hyderabad. | 10-02-2022 upto 13:00 hrs | |
TIFR/PD/CF21-137/211557 | Construction of CC & Paver block road at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid Meeting on Feb 10, 2022 - 11:00 Hrs | 14-02-2022 upto 13:00 hrs | |
TIFR/PD/CF21-134/211521 | Construction of MS Structure for Petawatt Building at Plot-B, TIFR, Hyderabad. Pre Bid Meeting on Feb 7, 2022 - 11:00 Hrs | 10-02-2022 upto 13:00 hrs | |
TIFR/PD/CF21-102/211207 | DUE DATE EXTENSION FOR PROVIDING TRANSPORT SERVICES (EICHER or EQUIVALENT - 30 SEATER BUS) FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD. | 31-01-2022 upto 13:00 hrs | |
TIFR/PD/CA21-22/21-22/210022 | CORRIGENDUM NO. 1 for Supply, Installation and Commissioning of a High-Performance Computing (HPC) Cluster for TIFR Hyderabad. | 28-02-2022 upto 13:00 hrs | |
TIFR/PD/CA21-185/21-22/211316 | CORRIGENDUM NO. 1 for Supply, Installation and Commissioning of Big Data Servers for TIFR Hyderabad. | 11-02-2022 upto 13:00 hrs | |
TIFR/PD/CA21-185/21-22/211316 | Supply, Installation and Commissioning of Big Data Servers for TIFR Hyderabad. Pre Bid Meeting on Jan 24, 2021 - 12:00 PM | 11-02-2022 upto 13:00 hrs | |
TIFR/PD/CA21-23/21-22/210023 | Supply, Installation and Commissioning of Nvidia A100 80GB or higher GPU based server with NVLink interconnect for TIFR Hyderabad. Pre Bid Meeting on Jan 24, 2021 - 11:30 AM | 11-02-2022 upto 13:00 hrs | |
TIFR/PD/CA21-22/21-22/210022 | Supply, Installation and Commissioning of a High-Performance Computing (HPC) Cluster for TIFR Hyderabad. Pre Bid Meeting on Jan 24, 2021 - 11:00 AM | 11-02-2022 upto 13:00 hrs | |
TIFR/PD/CA21-199/211400 | Supply, Installation, Testing & Commissioning of PUF Panels, Air Shower, Passbox, and other related works for Animal Facility in Hanger Building-2, at TIFR, Hyderabad. Pre Bid Meeting on Jan 24, 2021 - 11:00 AM | 02-02-2022 upto 13:00 hrs | |
TIFR/PD/GT/TS/CF-21/19021 | Prequalification -EOI for Providing Comprehensive Consultancy Services for setting up a State of the art Academic cum Residential Campus for TIFR at Hyderabad, Telangana, India | ||
TIFR/PD/CF21-102/211207 | DUE DATE EXTENSION FOR PROVIDING TRANSPORT SERVICES (EICHER or EQUIVALENT - 30 SEATER BUS) FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD. | 24-01-2022 upto 13:00 hrs | |
TIFR/PD/CF21-102/211207 | TENDER FOR PROVIDING TRANSPORT SERVICES (EICHER OR EQUIVALENT - 30 SEATER BUS) TO TIFR, HYDERABAD. | 18-01-2022 upto 13:00 hrs | |
TFR/PD/CF21-120/211358 | Construction of Sub Structure for Petawatt Building at Plot-B, TIFR, Hyderabad. Pre Bid Meeting on Jan 20, 2021 - 11:00 AM | 25-01-2022 upto 13:00 hrs | |
TIFR/PD/CA21-177/211264 | CORRIGENDUM-I for Supply, Installation, Testing and Commissioning of Air Conditioning works for Bio Lab, Mezzanine Floor in Hanger Building-2 at Plot-B, TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 10-01-2022 | |
TIFR/PD/CF21-98/211173 | CORRIGENDUM-I FOR PROVIDING CATERING AND SERVING SERVICES FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD. | 07-01-2022 upto 13:00 hrs | |
TIFR/PD/CA21-177/211264 | Letter of Enquiry and BOQ for Supply, Installation, Testing, and Commissioning of Air Conditioning works for Bio Lab, Mezzanine Floor in Hanger Building-2 at Plot-B, TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 05-01-2022 | |
TIFR/PD/CA21-174/211214 | Letter of Enquiry and BOQ for Supply, Installation, Testing, and Commissioning of Air Conditioning works & Electrical works for Dr. Pabitra K Nayak's Lab in Hanger Building-1 at Plot-B, TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 27-12-2021 | |
TIFR/PD/GT/CA21-153/211033 | Corrigendum No. 3 for Supply, Installation and Commissioning of High-Performance Computing Cluster for TIFR Hyderabad | 22-12-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-98/211173 | TENDER FOR PROVIDING CATERING AND SERVING SERVICES FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD | 07-01-2022 upto 13.00 Hrs. | |
TIFR/PD/CA21-172/211198 | Supply, Installation, Testing, and Commissioning of PUF Panels, Air Shower, Passbox, and other related works Animal Facility in Hanger Building-2 at Plot-B, TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid Meeting on Dec 20, 2021 - 11:00 AM | 23-12-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-101/211196 | Construction of Open Lab and Office space Interior for Hanger Building - II at plot B,Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District,Hyderabad. Pre Bid Meeting on Dec 23, 2021 - 11:30 AM | 30-12-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-100/211195 | Construction of BSL-2 Lab and Allied Interior Works for Hanger Building - II at plotB, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga ReddyDistrict, Hyderabad. Pre Bid Meeting on Dec 23, 2021 - 11:00 AM | 30-12-2021 upto 13.00 Hrs. | |
TIFR/PD/GT/CA21-153/211033 | Corrigendum No. 2 for Supply, Installation and Commissioning of High-Performance Computing Cluster for TIFR Hyderabad. | 20-12-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-169/211154 | Enquiry Letter and BOQ for Supply, Installation, Testing & Commissioning of Air Conditioning System works for Hostel Block-II at Plot-B, Survey No.36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad-500046 | 17-12-2021 | |
TIFR/PD/CA21-158/211059 | CORRIGENDUM-I for Supply, Installation, Testing & Commissioning of HVAC System and other related works for Animal Facility in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 13-12-2021 by 13:00 Hrs | |
TIFR/PD/CF21-85/211037 | CORRIGENDUM-I Supply, Installation, Testing, and Commissioning of Internal Electrification and other related works for Animal Facility, Ground Floor, Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 02-12-2021 by 13:00 Hrs | |
TIFR/PD/GT/CA21-153/211033 | Corrigendum No. 1 for Supply, Installation and Commissioning of High-Performance Computing Cluster for TIFR Hyderabad. | 13-12-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-158/211059 | Supply, Installation, Testing and Commissioning of HVAC System and other related works for Animal Facility in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid Meeting on Nov 29, 2021 - 11:00 AM | 06-12-2021 by 13:00 Hrs. | |
TIFR/PD/CF21-85/211037 | Supply, Installation, Testing, and Commissioning of Internal Electrification and other related works for Animal Facility, Ground Floor, Hanger Building-2 at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 25-11-2021 upto 13.00 hrs | |
TIFR/ADM/CF21-86/211039 | TENDER FOR PROVIDING ROUND THE CLOCK SECURITY SERVICES FOR TIFR CAMPUS AT GOPANPALLY, HYDERABAD. | 07-12-2021 upto 13.00 hrs | |
TFR/PD/GT/IC20-9/200483 | Petawatt laser - Supply, Installation, and Commissioning at Tata Institute of Fundamental Research, Hyderabad. | 17-01-2022 upto 13.00 hrs | |
TIFR/PD/GT/CA21-153/211033 | Supply, Installation and Commissioning of High-Performance Computing Cluster for TIFR Hyderabad. Pre Bid Meeting on Nov 22, 2021 - 11:00 AM | 13-12-2021 upto 13.00 hrs | |
TIFR/PD/CA21-143/210972 | CORRIGENDUM FOR Supply, Installation, Testing, and Commissioning of Air Distribution System and other related works for Animal Facility in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. | 22-11-2021 upto 13.00 hrs | |
TIFR/PD/CA21-143/210972 | Supply, Installation, Testing and Commissioning of Air Distribution System and other related works for Animal Facility in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village),Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid Meeting on Nov 12, 2021 - 11:00 AM | 17-11-2021 by 13:00 Hrs | |
TIFR/PD/IC21-10/21-22/210010 | Supply, Installation and Commissioning of 12T Cryogen- free Dilution Refrigerator with Bottom load-lock for TIFR Hyderabad. | 30-11-2021 upto 13.00 hrs | |
TIFR/PD/CM21-672/210974 | Tender Enquiry for Supply of Electrical Material as per BOQ for TIFR Hyderabad | 15-11-2021 | |
TIFR/PD/CF21-80/210917 | Civil & Aluminum work at Hanger 1 plot B, Survey No. 36/P, Gopanpally Village,Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 03-11-2021 upto 13.00 Hrs. | |
TIFR/PD/WO21-08/21-22/210008 | Engagement of Clearing and Forwarding Agency for Customs Clearance of Imported Consignments for TIFR Hyderabad. | 16-11-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-109/210815 | Corrigendum-I for Supply, Installation, Testing & Commissioning of Air Conditioning and other related works for Biosafety Level (BSL) Lab-2 in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046 | 25-10-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-106/21-22/210802 | Supply, Installation and Commissioning of Quadrupole-Time Of Flight Liquid Chromatography Mass Spectrometry/Mass Spectrometer System (Q-TOF LC-MS/MS system) with dual ionization source for qualitative and quantitative metabolomics and lipidomics for TIFR Hyderabad. | 08-11-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-109/210815 | Supply, Installation, Testing and Commissioning of Air Conditioning System and other related works for Biosafety Level (BSL) Lab-2 in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Pre Bid Meeting on Oct 14, 2021 - 11:00 AM | 18-10-2021 by 13:00 Hrs | |
TIFR/PD/CA21-105/210800 | Tender Enquiry for Supply of " Laboratory Bench type Fume Hoods" for Tata Institute of Fundamental Research, Hyderabad. | 18-10-2021 | |
TFR/PD/CF21-77/210789 | Civil & Structural work for Raw and RO Water Plant at Plot-B, TIFR, Hyderabad. Pre Bid Meeting on Oct 11, 2021 - 11:00 AM | 20.10.2021 upto 13:00 Hrs. | |
TIFR/PD/CA21-103/210790 | Supply, Installation, Testing & Commissioning of Air Conditioning System and other related works for Dr. Pabitra K. Nayak's Lab in Hanger Building-1, Ground Floor, Plot-B, TIFR Hyderabad. | 13-10-2021 | |
TIFR/PD/CA21-93/210757 | Supply, Installation & Commissioning of "Modular Workbench with Specifications" for Tata Institute of Fundamental Research, Hyderabad. | 13-10-2021 | |
TIFR/PD/CA21-83/210694 | Supply, Installation & Commissioning of "Modular Workbench with Specifications" for Tata Institute of Fundamental Research, Hyderabad. | 13-10-2021 | |
TIFR/PD/CA21-06/21-22/210006 | Supply of High Performance Microwave Synthesis System with Specifications for Tata Institute of Fundamental Research, Hyderabad. | 14-10-2021 | |
TIFR/PD/CF21-72/210716 | Corrigendum – I for Interior Furniture & Amenities works at Hostel Block - II, TIFR, Hyderabad | 07-10-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-74/210736 | Supply, Installation, Testing & Commissioning of Internal Electrification, and other related works for Hostel Block-II at Plot-B, TIFR Hyderabad, Survey No.36/P, Gopanapally Village, Serilingampally Mandal, Ranga Reddy Dist, Hyderabad - 500 046. Pre Bid Meeting on Oct 06, 2021 - 11:00 AM | 12-10-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-72/210716 | Interior Furnishing & Amenities works for Hostel Block -II at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad Pre Bid Meeting on Sep 29, 2021 - 11:30 AM | 07-10-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-70/210709 | Construction of Civil Super Structure for Hostel Block -II at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad Pre Bid Meeting on Sep 29, 2021 - 11:00 AM | 07-10-2021 upto 13.00 Hrs. | |
TIFR/PD/IC21-05/21-22/210005 | Supply, Installation and Commissioning of Steady State and Time-Correlated Single Photon Counting (TCSPC) Fluorescence Spectrometer for TIFR Hyderabad | 12-10-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-59/210509 | Supply, Installation, Testing and Commissioning of Air Conditioning System and other related works to maintain 1lakh cleanroom class for BSL lab in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad-500046. Telangana Pre Bid Meeting on Aug 27, 2021 - 11:00 AM to 11:30 AM India | 01-09-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-47/210428 | Annual Maintenance Contract for deploying Manpower for Plumbing/Carpentry Works/Operation & Maintenance of STP at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), RR Dist., Hyderabad-500046 Opening of Technical Bids on Aug 30, 2021 - 03:00 PM India | 30-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-46/210420 | Construction of MS Structure and Roofing Work for Hostel Block -II at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Pre Bid Meeting on Aug 06, 2021 - 11:00 AM India | 11-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-48/210411 | Supply, Installation, Testing and Commissioning of Air Conditioning Systems and other related works for Biology Labs in Hanger Building-2, at TIFR, Plot-B, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), RR Dist, Hyderabad-500046. Technical Bid Opening on Aug 09, 2021 - 03:00 PM India | 09-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-30/210179 | Supply, Installation, Testing and Commissioning of Fire Alarm & Detection system and all other related works for Hanger Building-2. Technical Bid Opening on Aug 06, 2021 - 03:00 PM India | 06-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-45/210383 | Supply, Installation, Testing and Commissioning of Internal Electrification and all related works For Biology Lab at Mezzanine Floor in Hanger Building-2 at TIFR, Plot-B, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. Price Bid Opening on Aug 09, 2021 - 03:00 PM India | 05-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CA21-36/210293 | Supply, Installation and Commissioning of State of the Art 900 MHz NMR Spectrometer to carry out solid and solution state NMR experiments for TIFR Hyderabad. | 11-08-2021 upto 13.00 Hrs. | |
TIFR/PD/CF21-21/210150 | Interior Works for Hanger Building II at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Pre Bid Meeting on Jun 22, 2021 - 03:00 PM India | 29-06-2021 upto 13:00 Hrs. | |
TIFR/PD/TS/9038 | Corrigendum-I for Landscaping Works for Hostel Block -I at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 10-05-2021 upto 13:00 Hrs. | |
TIFR/PD/TS/9036 | Supply and installation of Structural Glazing for Hostel Block -I at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Pre Bid Meeting on May 05, 2021 - 11:00 AM India | 07-05-2021 upto 13:00 Hrs. | |
TIFR/PD/TS/9038 | Landscaping Works for Hostel Block -I at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Pre Bid Meeting on May 04, 2021 - 11:00 AM India | 06-05-2021 upto 13:00 Hrs. | |
TIFR/PD/TS/9037 | Supply of Cot for Hostel Block -I at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Pre Bid Meeting on May 03, 2021 - 11:30 AM India | 05-05-2021 upto 13:00 Hrs. | |
TIFR/PS/TS/9035 | Supply and installation of Study table, Wardrobe and Chairs for Hostel Block -I at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad Pre Bid Meeting on Apr 15, 2021 - 11:00 AM India | 20-04-2021 upto 13:00 Hrs. | |
TIFR/PD/RC21-22/200001 | Corrigendum No. 1 for Rate Contract For the Chemicals, Glassware’s and Lab wares for TIFR Hyderabad.Rate Contract Period – One Year with Effect From 01.04.2021 to 31.03.2022 | 19-04-2021 upto 13.00 Hrs | |
TIFR/PD/RC21-22/200001 | Rate Contract For the Chemicals, Glassware and Lab wares for TIFRH. Rate Contract Period – One Year with Effect From 01.04.2021 to 31.03.2022 | 14-04-2021 | |
TIFR/PD/IC20-10/20010 | Corrigendum No. 1 for Supply and Installation of Ion milling/Sputtering high vacuum chamber with ECR Ion gun with Einzel lens for Tata Institute of Fundamental Research, Hyderabad. | 15-03-2021 upto 13:00 Hrs. | |
TIFR/PD/CA20-90/201040 | Corrigendum No - 1 for Supply, Installation, Testing and Commissioning of Cassette ACs and all related works at Hanger Building-1, TIFR, Plot-B, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. Technical Bid Opening on Mar 08, 2021 - 03:00 PM India | 08-03-2021 upto 13:00 Hrs. | |
TIFR/PD/CA20-27/200399 | Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad. Pre-bid meeting on Mar 09, 2021 - 11:00 AM India BIDDERS WILL NOT BE ALLOWED TO JOIN AFTER 11.00 AM | 30-03-2021 upto 13.00 Hrs. | |
TIFR/PD/CA20-90/201040 | Supply, Installation, Testing and Commissioning of Cassette ACs and all related works at Hanger Building-1, TIFR, Plot-B, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. | 05-03-2021 upto 13:00 Hrs. | |
TIFR/PD/CF20-104/201031 | Construction of MS Structure and Roofing Work for Hostel Block -II at plot B, Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. opening of technical bids on Mar 09, 2021 - 03:00 PM India | 09-03-2021 upto 13:00 Hrs. | |
TFR/PD/CF20-95/200981 | Annual Maintenance Contract for Outsourcing Manpower for Maintenance of Horticulture, Landscaping and supply of related materials at TIFRH-Hyderabad. opening of price bids on Feb 24, 2021 - 03:00 PM India | 23-02-2021 upto 13:00 Hrs. | |
TIFR/PD/IC20-12/20012 | Supply, Installation and Commissioning of Crystallization Screening Robotic System With Accessories | 09-03-2021 upto 13:00 Hrs. | |
TIFR/PD/IC20-10/20010 | Supply, Installation and Commissioning of Ion milling/sputtering high vacuum chamber with ECR Ion gun with Einzel Lens | 08-03-2021 upto 13:00 Hrs. | |
TIFR/PD/IC20-08/20008 | Corrigendum No. 2 for Supply, Installation and Commissioning of GPU Based High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad | 10-02-2021 upto 13:00 Hrs. | |
TIFR/PD/CF20-80/200845 | Supply, Installation, Testing and Commissioning of Internal Electrification and all related works in Hostel Block -1 at TIFR, Plot-B, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046 Price Bid Opening on Feb 05, 2021 - 03:30 PM India | 03-02-2021 upto 13.00 Hrs. | |
TIFR/PD/IC20-08/20008 | Corrigendum No. 1 for Supply, Installation and Commissioning of GPU Based High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad | 03-02-2021 upto 13.00 Hrs. | |
TIFR/PD/CF20-69/200735 | Corrigendum for Construction of Civil Structure, Interior and Plumbing Work for Guest House & Hostel at plot B, No. Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Join for opening of the Financial bid on Jan 28, 2021 - 11:00 AM India | 25-01-2021 upto 13.00 Hrs. | |
TIFR/PD/CF20-74/200779 | Construction of Sub Structure for Hostel Block -II at plot B, No. Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Join opening of Financial Bid on Jan 27, 2021 - 03:00 PM India | 25-01-2021 upto 13.00 Hrs. | |
TIFR/PD/IC20-08/20008 | Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad. Join the pre-bid meeting on Jan 19, 2021 - 11:00 AM India BIDDERS WILL NOT BE ALLOWED TO JOIN AFTER 11.00 AM | 03-02-2021 upto 13.00 Hrs. | |
TFR/PD/CF20-69/200735 | Construction of Civil Structure, Interior and Plumbing Work for Guest House & Hostel at plot B, TIFR, Hyderabad. Join for Pre-Bid Meeting on Jan 18, 2021 03:00 PM India | 25-01-2021 upto 13.00 Hrs. | |
TIFR/PD/TS/9030 | Corrigendum 1 for Construction of MS Structure and Roofing work for Guest House & Hostel at plot B, No. Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 12-01-2021 upto 13.00 Hrs. | |
TIFR/PD/TS/9030 | Construction of MS Structure and Roofing work for Guest House & Hostel at plot B, No. Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. Join for Pre-Bid Meeting on Jan 05, 2021 03:00 PM India | 12-01-2021 upto 13.00 Hrs. | |
TIFR/PD/TS/9029 | Construction of Sub Structure for Guest House & Hostel at plot B, No. Survey No. 36/P, Gopanpally Village,Serilingampally Mandal, Ranga Reddy District, Hyderabad. Join for Public Tender opening on Jan 06, 2021 03:00 PM India | 06-01-2021 upto 13.00 Hrs. | |
TIFR/PD/CF20-48/200530 | Corrigendum 2 Against Tender Ref. No. TIFR/PD/CF20-48/200530 Construction of Lead Room of size 2.5*2.5*2.675mtrs at TIFR, FReTB Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046 | 29-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-11/200522 | Supply, Installation and Commissioning of Turbo Molecular Pump for Tata Institute of Fundamental Research, Hyderabad. | 06-01-2021 upto 13.00 Hrs. | |
TIFR/PD/IC20-9/200483 | Corrigendum No. 3 for Supply, Installation and Commissioning of Ti:Sapphire Laser System of Peta-Watt class power for Tata Institute of Fundamental Research, Hyderabad | 14-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-30/200490 | Corrigendum No. 3 for Supply, Installation and Commissioning of Spinning Disk Confocal System with Super ResolutionImaging for Tata Institute of Fundamental Research, Hyderabad | 10-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-07/20007 | Corrigendum No. 3 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for Tata Institute of Fundamental Research, Hyderabad | 09-12-2020 upto 13.00 Hrs. | |
TFR/PD/CA20-27/200399 | Corrigendum No. 4 for Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad | 08-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CF20-48/200530 | CORRIGENDUM No. 1 Against Tender Ref. No. TIFR/PD/CF20-48/200530 dated 23-11-2020 for Construction of Lead Room of size 2.5*2.5*2.675mtrs at TIFR, FReTB Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046 Join for Pre-Bid Meeting on Dec 04, 2020 11:00 AM India | 22-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CF20-47/200518 | CORRIGENDUM No. 1 Against Tender Ref. No. TIFR/PD/CF20-47/200518 dated 24-11-2020 for Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical & Fire Safety installations on 24 x 7 basis” on all days at TIFR, FReTB, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. join for opening of Price bids on Jan 01, 2021 12:00 PM India | 15-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-9/200483 | Corrigendum No. 2 for Supply, Installation and Commissioning of Ti:Sapphire Laser System of Peta-Watt class power for Tata Institute of Fundamental Research, Hyderabad | 14-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-30/200490 | Corrigendum No. 2 for Supply, Installation and Commissioning of Spinning Disk Confocal System with Super ResolutionImaging for Tata Institute of Fundamental Research, Hyderabad | 10-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-07/20007 | Corrigendum No. 2 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for Tata Institute of Fundamental Research, Hyderabad | 09-12-2020 upto 13.00 Hrs. | |
TFR/PD/CA20-27/200399 | Corrigendum No. 3 for Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad | 08-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CF20-47/200518 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical & Fire Safety installations on 24 x 7 basis” on all days at TIFR, FReTB, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. join for opening of Price bids on Jan 01, 2020 12:00 PM India | 15-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CF20-48/200530 | Construction of Lead Room of size 2.5*2.5*2.675mtrs at TIFR, FReTB Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad-500046. | 22-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-27/200399 | Corrigendum No. 2 for Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad | 08-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-9/200483 | Corrigendum No. 1 for Supply, Installation and Commissioning of Ti:Sapphire Laser System of Peta-Watt class power for Tata Institute of Fundamental Research, Hyderabad | 14-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-30/200490 | Corrigendum No. 1 for Supply, Installation and Commissioning of Spinning Disk Confocal System with Super Resolution Imaging for Tata Institute of Fundamental Research, Hyderabad | 10-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-07/20007 | Corrigendum No. 1 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for Tata Institute of Fundamental Research, Hyderabad Join for Pre-Bid Meeting on Nov 23, 2020 11:00 AM India BIDDERS WILL NOT BE ALLOWED TO JOIN AFTER 11.00 AM | 09-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-27/200399 | Corrigendum No. 1 for Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad Join for Pre-Bid Meeting on Nov 19, 2020 11:00 AM India | 08-12-2020 upto 13.00 Hrs | |
TIFR/PD/IC20-9/200483 | Supply, Installation and Commissioning of Ti:Sapphire Laser System of Peta-Watt class power for Tata Institute of Fundamental Research, Hyderabad | 14-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-30/200490 | Supply, Installation and Commissioning of Spinning Disk Confocal System with Super Resolution Imaging for Tata Institute of Fundamental Research, Hyderabad | 10-12-2020 upto 13.00 Hrs. | |
TIFR/PD/IC20-07/20007 | Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for Tata Institute of Fundamental Research, Hyderabad Join for Pre-Bid Meeting on Nov 23, 2020 11:00 AM India BIDDERS WILL NOT BE ALLOWED TO JOIN AFTER 11.00 AM | 09-12-2020 upto 13.00 Hrs. | |
TIFR/PD/CA20-27/200399 | Supply, Installation and Commissioning of High-Performance Computing (HPC) Cluster for Tata Institute of Fundamental Research, Hyderabad Join for Pre-Bid Meeting on Nov 19, 2020 11:00 AM India | 08-12-2020 upto 13.00 Hrs | |
TIFR/PD/TS/9014 | Flooring work in Hanger Building-II at plot B, TIFR 36/P, Gopanpally Village, Serilingampally Mandal, Ranga ReddyDistrict, Hyderabad, Telangana 500046 Join Meeting on Dec 10, 2020 12:00 PM India | 27-11-2020 | |
TIFR/PD/CF20-31/200407 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of HVAC installations on 24 x 7 basis” on all days at TIFR, FReTB, Survey No. 36/P, Gopanpally (Village),Serilingampally(Mandal), RR Dist, Hyderabad-500046. Opening of Price bids meeting on Nov 20, 2020 11:00 AM India | 06-11-2020 by 13.00 Hrs | |
TFR/PD/CM20-265/200337 | Supply, Installation, testing and commissioning of the indoor type 33KV Single - Phase Current Transformer (CT) AND Single-Phase Potential Transformer(PT) to TIFR, Hyderabad | 21-09-2020 by 10.00 Hrs | |
TIFR/PD/CF20-19/200276 | Annual Maintenance Contract for deploying Manpower for Plumbing/Carpentry Works/Operation & Maintenance of STP at TIFR, Survey No. 36/P, Gopanpally (Village), Serilingampally (Mandal), RR Dist., Hyderabad-500046. | 09-09-2020 by 13.00 Hrs | |
PUBLIC TENDER NOTICE | 02-08-2020 | ||
TFR/PD/IC19-28/19028 | Corrigendum No. 4 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad | 11-08-2020 upto 13.00 Hrs | |
TFR/PD/IC19-47/190986 | Corrigendum No. 4 for Supply, Installation, Commissioning of Bench-top EPR Spectrometer for TIFR Hyderabad | 10-08-2020 upto 13.00 Hrs. | |
TFR/PD/IC19-48/190991 | Corrigendum No. 4 for Supply, Installation, Commissioning of 2-Port Glove Box Work Station for TIFR Hyderabad. | 06-08-2020 upto 13.00 Hrs | |
TFR/PD/IC19-26/19026 | Corrigendum No. 4 for Supply, Installation, Commissioning of Modulated differential scanning calorimetry (DSC) with Specifications for TIFR Hyderabad. | 05-08-2020 upto 13.00 Hrs | |
TFR/PD/IC19-25/19025 | Corrigendum No. 4 for Supply, Installation, Commissioning of Thermogravimetric Analysis (TGA) Instrument with High Resolution and Modulated Specifications for TIFR Hyderabad. | 04-08-2020 upto 13.00 Hrs | |
TFR/PD/IC19-27/19027 | Corrigendum No. 4 for Supply, Installation, Commissioning of X-Ray Photoelectron Spectroscopy (XPS) for TIFR Hyderabad. | 03-08-2020 upto 13.00 Hrs | |
TFR/PD/IC19-47/190986 | Corrigendum 3 for Supply, Installation, Commissioning of Bench-top EPR Spectrometer for TIFR Hyderabad. | 24-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-48/190991 | Corrigendum 3 for Supply, Installation, Commissioning of 2-Port Glove Box Work Station for TIFR Hyderabad. | 23-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-28/19028 | Corrigendum 3 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad. | 22-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-26/19026 | Corrigendum 3 for Supply, Installation, Commissioning of Modulated differential scanning calorimetry (DSC) with Specifications for TIFR Hyderabad. | 18-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-25/19025 | Corrigendum 3 for Supply, Installation, Commissioning of Thermogravimetric Analysis (TGA) Instrument With High Resolution and Modulated Specifications for TIFR Hyderabad. | 17-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-27/19027 | Corrigendum 3 for Supply, Installation, Commissioning of X-Ray Photoelectron Spectroscopy (XPS) for TIFR Hyderabad. | 16-06-2020 upto 13:00 Hrs | |
TFR/PD/RC20-21/200001 | Corrigendum 2 for Rate Contract For the Chemicals, Glassware’s and Lab wares for TIFR Hyderabad.Rate Contract Period – One Year with Effect From 01.04.2020 to 31.03.2021 | 15-06-2020 upto 13:00 Hrs | |
TFR/PD/IC19-47/190986 | Corrigendum 2 for Supply, Installation, Commissioning of Bench-top EPR Spectrometer for TIFR Hyderabad. | 25-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-48/190991 | Corrigendum 2 for Supply, Installation, Commissioning of 2-Port Glove Box Work Station for TIFR Hyderabad. | 22-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-28/19028 | Corrigendum 2 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad. | 21-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-26/19026 | Corrigendum 2 for Supply, Installation, Commissioning of Modulated differential scanning calorimetry (DSC) with Specifications for TIFR Hyderabad. | 20-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-25/19025 | Corrigendum 2 for Supply, Installation, Commissioning of Thermogravimetric Analysis (TGA) Instrument With High Resolution and Modulated Specifications for TIFR Hyderabad. | 19-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-27/19027 | Corrigendum 2 for Supply, Installation, Commissioning of X-Ray Photoelectron Spectroscopy (XPS) for TIFR Hyderabad. | 18-05-2020 upto 13:00 Hrs | |
TFR/PD/RC20-21/200001 | Corrigendum 1 for Rate Contract For the Chemicals, Glassware’s and Lab wares for TIFR Hyderabad.Rate Contract Period – One Year with Effect From 01.04.2020 to 31.03.2021. | 11-05-2020 upto 13:00 Hrs | |
TFR/PD/IC19-47/190986 | Corrigendum No.1 for Supply, Installation, Commissioning of Bench-top EPR Spectrometer for TIFR Hyderabad. | 29-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-48/190991 | Corrigendum No.1 for Supply, Installation, Commissioning of 2-Port Glove Box Work Station for TIFR Hyderabad. | 28-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-28/19028 | Corrigendum No.1 for Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad. | 27-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-26/19026 | Corrigendum No.1 for Supply, Installation, Commissioning of Modulated differential scanning calorimetry (DSC) with Specifications for TIFR Hyderabad. | 23-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-25/19025 | Corrigendum No.1 for Supply, Installation, Commissioning of Thermogravimetric Analysis (TGA)Instrument With High Resolution and Modulated Specifications for TIFR Hyderabad. | 22-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-27/19027 | Corrigendum No. 1 for Supply, Installation, Commissioning of X-Ray Photoelectron Spectroscopy (XPS) for TIFR Hyderabad. | 21-04-2020 upto 13:00 Hrs | |
TFR/PD/RC20-21/200001 | Rate Contract For the Chemicals, Glassware’s and Lab wares for TIFR Hyderabad.Rate Contract Period – One Year with Effect From 01.04.2020 to 31.03.2021 | 15-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-47/190986 | Supply, Installation, Commissioning of Bench-top EPR Spectrometer for TIFR Hyderabad. | 08-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-26/19026 | Supply, Installation, Commissioning of Modulated differential scanning calorimetry (DSC) with Specifications for TIFR Hyderabad. | 08-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-48/190991 | Supply, Installation, Commissioning of 2-Port Glove Box Work Station for TIFR Hyderabad. | 07-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-25/19025 | Supply, Installation, Commissioning of Thermogravimetric Analysis (TGA)Instrument With High Resolution and Modulated Specifications for TIFR Hyderabad. | 07-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-28/19028 | Supply, Installation and Commissioning of GPU based High Performance Computing Cluster for TIFR Hyderabad. | 06-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-27/19027 | Supply, Installation, Commissioning of X-Ray Photoelectron Spectroscopy(XPS) for TIFR Hyderabad. | 06-04-2020 upto 13:00 Hrs | |
TFR/PD/IC19-24/19024 | Supply, Installation and Commissioning of Compute Nodes for a High Performance Computing (HPC) Cluster for TIFR Hyderabad | 02-03-2020 upto 13.00 Hrs | |
TIFR/PD/CF19-121/190973 | Annual Maintenance Contract for Engaging of Two Unskilled Gardener for maintenance of Horticulture and landscapling work at TIFR, FReTB, Survey No. 36/P, Gopanpally(Village), Serilingampally(Mandal), RR Dist, Hyderabad - 500046 | 24-02-2020 upto 13:00 Hrs | |
TFR/PD/CA19-86/190853 | Corrigendum 1 Enquiry letter for supply of AMD Epyc based HPC Cluster with five years warranty - 01No to TIFR, Hyderabad | 24-02-2020 | |
TFR/PD/CA19-86/190853 | Enquiry letter for supply of AMD Epyc based HPC Cluster with five years warranty - 01No to TIFR, Hyderabad | 24-02-2020 | |
TIFR/PD/GT/TS/CF-21/19021 | Clarification for the work of “Expression of Interest for providing Comprehensive Consultancy Services for setting up a State of the art Academic cum Residential campus for TIFR at Hyderabad, Telangana, India.” | 10-02-2020 upto 15:00 Hrs | |
TIFR/PD/CA19-88/190878 | Enquiry letter for supply of Cyclic Voltammetry with specifications - 01No to TIFR, Hyderabad | 03-02-2020 | |
TFR/PD/CA19-23/19023 | Enquiry letter for supply, installation, testing, commissioning, integration and training on video conference equipment to build state of the art E-class room for TIFR, Hyderabad | 06-02-2020 at 13:00 Hrs | |
TFR/PD/CF19-107/190831 | Electrical Works for Hanger Building - II in Plot - B, at TIFR, Hyderabad | 22-01-2020 upto 13:00 Hrs. | |
TFR/PD/TS/9010 | Construction of Hanger Building-2 Super Structure Work in Plot-B at TIFR, Hyderabad. | 31-12-2019 upto 17:00 Hrs. | |
TIFR/PD/GT/TS/CF-21/19021 | EOI for Providing Comprehensive Consultancy Services for setting up a State of the art Academic cum Residential Campus for TIFR at Hyderabad, Telangana, India | 10-02-2020 upto 15:00 Hrs. | |
TFR/PD/IC19-35/ 190789 | Corrigendum No. 1 for Supply, Installation, Commissioning of Upright Spectral Confocal Microscope System Upgradable with High Resolution Attachments for TIFR Hyderabad. | 20-01-2020 upto 13:00 Hrs. | |
TFR/PD/IC19-35/ 190789 | Supply, Installation, Commissioning of Upright Spectral Confocal Microscope System Upgradable with High Resolution Attachments for TIFR Hyderabad. | 20-01-2020 upto 13:00 Hrs. | |
TFR/PD/IC19-19/19019 | Supply, Installation, Commissioning of High Resolution X-Ray Diffractometer of Thin Film Analysis for TIFR Hyderabad. | 20-01-2020 upto 13:00 Hrs. | |
TFR/PD/IC19-32/190729 | Supply, Installation, Commissioning of Turbo Molecular Pumps for UHV Application for TIFR Hyderabad. | 21-01-2020 upto 13:00 Hrs. | |
TFR/PD/IC19-31/190704 | Supply, Installation, Commissioning of Auger Electron Spectrometer for TIFR Hyderabad. | 21-01-2020 upto 13:00 Hrs. | |
TFR/PD/CF19-92/190775 | Construction of Hanger Building-2 ( MS Structure & Roofing works) in Plot-B at TIFR, Hyderabad. | 10-01-2020 upto 17:00 Hrs. | |
TFR/PD/TS/9010 | Construction of Hanger Building-II (Superstructure) in Plot-B at TIFR, Hyderabad. | 31-12-2019 upto 17:00 Hrs. | |
TFR/PD/TS/9009 | Construction of Hanger Building-2 (Substructure Work) in Plot-B at TIFR, Hyderabad. | 30-12-2019 upto 17:00 Hrs. | |
TFR/PD/IC19-18/19018 | Supply, Installation, Commissioning of A state-of-the-art Ultra Microtome for the facility to generate ultra-thin sections for TEM imaging for TIFR Hyderabad. | 04-11-2019 upto 13.00 Hrs. | |
TFR/PD/IC19-17/19017 | Supply, Installation, Commissioning of Floor Model Ultra and 4 Litre Floor Model High Speed Centrifuge for TIFR Hyderabad. | 04-11-2019 upto 13.00 Hrs. | |
TFR/PD/IC19-16/19016 | Supply, Installation, Commissioning of Laser Capture Microdissection System for TIFR Hyderabad. | 01-11-2019 upto 13.00 Hrs. | |
TFR/PD/IC19-03/19003 | Supply, Installation, Commissioning of automated high throughput system for NGS library preparation for RNA, immune profiling, surface marker protein, CRISPR, and ATAC applications at Single Cell resolution for TIFR Hyderabad. | 01-11-2019 upto 1300 hrs | |
TIFR/PD/190463/CF19-59 | TENDER FOR PROVIDING CATERING SERVICES TO TIFR HYDERABAD CAMPUS AT GOPANPALLY, HYDERABAD | 14-10-2019 at 1300 hrs | |
TIFR/PD/CF19-34/190228 | Corrigendum-1 for Annual Maintenance Contract for deploying Manpower for Plumbing and Carpentry Works at TIFR. | 05-08-2019 upto 13.00 Hrs | |
TIFR/PD/CF19-34/190228 | Annual Maintenance Contract for deploying Manpower for Plumbing and Carpentry Works at TIFR. | 01-08-2019 upto 13.00 Hrs | |
TIFR/PD/CF19-8/190034 | "Providing Transportation Services" to TIFR Hyderabad campus. | 20-05-2019 upto 17.30 Hrs | |
TFR/PD/IC18/F-707/180020 | Corrigendum No. 1 for Supply, Installation, Commissioning of 600 MHz Nuclear Magnetic Resonance Spectrometer for TIFR Hyderabad. | 29-03-2019 upto 13.00 Hrs | |
TFR/PD/IC18/F-707/180020 | Supply, Installation, Commissioning of 600 MHz Nuclear Magnetic Resonance Spectrometer for TIFR Hyderabad. | 22-03-2019 upto 13.00 Hrs | |
TIFR/ADM/CF18-122/180714 | Corrigendum No. 3 for TENDER FOR PROVIDING HOUSEKEEPING SERVICES FOR TIFR HYDERABAD CAMPUS AT GOPANPALLY, HYDERABAD. | 05-03-2019 upto 13.00 Hrs. | |
TIFR/ADM/CF18-122/180714 | Corrigendum No. 2 for TENDER FOR PROVIDING HOUSEKEEPING SERVICES FOR TIFR HYDERABAD CAMPUS AT GOPANPALLY, HYDERABAD. | 01-03-2019 upto 13.00 Hrs. | |
TIFR/ADM/CF18-122/180714 | Corrigendum No. 1 for TENDER FOR PROVIDING HOUSEKEEPING SERVICES FOR TIFR HYDERABAD CAMPUS AT GOPANPALLY, HYDERABAD. | 01-03-2019 upto 13.00 Hrs. | |
TIFR/ADM/CF18-122/180714 | TENDER FOR PROVIDING HOUSEKEEPING SERVICES FOR TIFR HYDERABAD CAMPUS AT GOPANPALLY, HYDERABAD. | 01-03-2019 upto 13.00 Hrs. | |
TFR/PD/IC18-28/F-431/180436 | Corrigendum No. 3 for Supply, Installation, Commissioning of 5 Axis Turn Mill Machine for TIFR Hyderabad. | 14-02-2019 upto 13.00 Hrs. | |
TFR/PD/IC18-29/F-432/180437 | Corrigendum No. 2 for Supply, Installation, Commissioning of Submerged Type Wire-Cut EDM Machine for TIFR Hyderabad. | 08-02-2019 upto 13.00 Hrs | |
TFR/PD/IC18-28/F-431/180436 | Corrigendum No. 2 for Supply, Installation, Commissioning of 5 Axis Turn Mill Machine for TIFR Hyderabad. | 07-02-2019 upto 13.00 Hrs | |
TFR/PD/IC18-29/F-432/180437 | Corrigendum No. 1 for Supply, Installation, Commissioning of Submerged Type Wire-Cut EDM Machine for TIFR Hyderabad. | 08-01-2019 upto 13.00 Hrs | |
TFR/PD/IC18-28/F-431/180436 | Corrigendum No. 1 for Supply, Installation, Commissioning of 5 Axis Turn Mill Machine for TIFR Hyderabad. | 07-01-2019 upto 13.00 Hrs | |
TFR/PD/IC18-33/F-468/180482 | Supply, Installation, Commissioning of Surface Plasmon Resonance Instrument for Real Time Detection of Biomolecular Interactions for TIFR Hyderabad | 27-11-2018 upto 13.00 Hrs | |
TFR/PD/IC18-29/F-432/180437 | Supply, Installation, Commissioning of Submerged Type Wire-Cut EDM Machine for TIFR Hyderabad | 26-11-2018 upto 13.00 Hrs | |
TFR/PD/IC18-28/F-431/180436 | Supply, Installation, Commissioning of 5 Axis Turn Mill Machine for TIFR Hyderabad | 26-11-2018 upto 13.00 Hrs | |
TFR/PD/IC18-27/F-430/180435 | Supply, Installation, Commissioning of Closed Cycle SQUID Instrument for TIFR Hyderabad | 26-11-2018 upto 13.00 Hrs | |
TFR/PD/IC18-26/F-395/180422 | Supply, Installation, Commissioning of Compute Nodes for High PerformanceComputing (HPC) Cluster for TIFR Hyderabad | 30-10-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-78/180373 | Construction of Steel Structure Mezzanine Floor for Hangar at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad | 23-10-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-85/180406 | Site Clearance of approximate 5.0 acres in Plot-B infront of FReT-B for immdiate infrastructure developements at Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad | 23-10-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-84/180405 | Construction of Powder coated Aluminium partition for individual laboratories on ground floor and Mezzanine floor ( PI Rooms and Student sitting area) in First Hangar Structure in Plot-B opposite to FReT-B at Survey No. 36/P, Gopanpally Village, Serilingampally Mandal, Ranga ReddyDistrict, Hyderabad | 24-10-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-86/180407 | Supply, installation, Testing and Commissioning of Internal electrification and all related works in lab areas of TIFR facility at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad-500107 | 29-10-2018 upto 13.00 Hrs | |
TIFR/ADM/CF18-73/180362 | TENDER FOR PROVIDING ROUND THE CLOCK SECURITY SERVICES FOR TIFR PERMANENT CAMPUS AT GOPANPALLY, HYDERABAD | 15-10-2018 upto 13.00 Hrs | |
TFR/PD/CHA/WO18-01/F-1/1001 | Engagement of Clearing and Forwarding Agency for Customs Clearance of Imported Consignments for TIFR Hyderabad Campus. | 30-07-2018 upto 13.00 Hrs | |
TFR/PD/IC18-14/F-222/180220 | Supply, Installation, Commissioning of Compact Confocal Module upgradable to Super-Resolution for TIFR Hyderabad. | 26-07-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-15/180113 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical & Fire Safety installations on 24 x 7 basis” on all days at TIFR, Hyderabad Campus. | 25-07-2018 upto 13.00 Hrs | |
TFR/PD/IC18-03/F-78/180078 | Corrigendum No. 2 for Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad. | 25-06-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-14/180109 | Annual Maintenance Contract for “Operation and Maintenance of Water Supply, Sewerage, Sanitation, Plumbing including servicing of Sanitary fittings & fixtures, Rain water Harvesting System and Fire fighting installations on 24 x 7 basis” on all days at TIFR, Hyderabad. | 19-06-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-16/180114 | Annual Maintenance Contract for “Operation and Maintenance of HVAC installations on 24 x 7 basis” on all days at TIFR, Hyderabad. | 21-06-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-15/180113 | Annual Maintenance Contract (AMC) for “Operation and Maintenance of Electrical & Fire Safety installations on 24 x 7 basis” on all days at TIFR, Hyderabad Campus. | 20-06-2018 upto 13.00 Hrs | |
TFR/PD/IC18-03/F-78/180078 | Corrigendum No.1 for Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad | 11-06-2018 upto 13.00 Hrs | |
TFR/PD/IC18-06/F-101/180099 | Supply, Installation, Commissioning of Pulsed Nd: YAG Laser System for TIFR Hyderabad | 12-06-2018 upto 13.00 Hrs | |
TFR/PD/IC18-03/F-78/180078 | Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad | 11-06-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-9/180080 | Corrigendum No. 1 for Providing Round the Clock Security Services for TIFR Permanent Campus at Gopanpally, Hyderabad | 31-05-2018 upto 13.00 Hrs | |
TIFR/PD/CF18-9/180080 | Tender for Providing Round the Clock Security Services for TIFR Permanent Campus at Gopanpally, Hyderabad | 31-05-2018 upto 13.00 Hrs | |
TFR/PD/IC17-04/F-714/217003 | Supply, Installation, Commissioning & Training of Sanger Sequencer andGenetic Analyzer for TIFR Hyderabad. | 16-03-2018 upto 13.00 Hrs | |
TFR/PD/IC17-03/F-713/217002 | Supply, Installation, Commissioning of Double Door Autoclave for TIFR Hyderabad. | 16-03-2018 upto 13.00 Hrs | |
TFR/PD/IC17-02/F-518/217001 | Supply, Installation, Commissioning of 600 MHz State of the Art Wide Bore NMR Spectrometers to Carry out High Resolution NMR Experiments in Solid State for TIFR Hyderabad. | 06-03-2018 upto 13.00 Hrs | |
TFR/PD/IC17-01/F-517/217000 | Corrigendum No. 2 for Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad. | 30-01-2018 upto 13.00 Hrs | |
TFR/PD/IC17-01/F-517/217000 | Corrigendum No. 1 for Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad. | 24-01-2018 upto 13.00 Hrs | |
TFR/PD/IC17-01/F-517/217000 | Supply, Installation, Commissioning of High Performance Computing (HPC) Cluster for TIFR Hyderabad. | 24-01-2018 upto 13.00 Hrs | |
TFR/PD/IC17-78/170491 | Supply, Installation, Commissioning of Glove Box Work Station for TIFR Hyderabad. | 04-01-2018 upto 13.00 Hrs | |
TFR/PD/IC17-77/170490 | Supply, Installation, Commissioning of Pulsed Dye Laser System and related accessories for TIFR Hyderabad. | 04-01-2018 upto 13.00 Hrs | |
TFR/PD/F-386/IC17-54/170376 | Supply, Installation, Commissioning and Training for Automated, High Speed, Multi-color Fluorescence Activated Cell Sorter (FACS) for TIFR Hyderabad. | 21-11-2017 upto 13.00 Hrs | |
TFR/PD/F-302/170294 | Construction of Hangar Structure for Housing Workshop & Laboratory Space at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 12-10-2017 upto 13.00 Hrs | |
TFR/PD/WO17/1001/PUB | Corrigendum No. 1 for Engagement of Clearing and Forwarding Agency for Customs Clearance of Imported Consignment. | 05-07-2017 upto 13.00 Hrs | |
TIFR/PD/FR17-1/170079 | Supply & Installation of Student Furniture for newly constructed First Research Building at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad | 15-06-2017 upto 13.00 Hrs | |
TFR/PD/WO17/1001/PUB | Engagement of Clearing and Forwarding Agency for Customs Clearance of Imported Consignment. | 20-06-2017 upto 13.00 Hrs | |
TFR/PD/F-730/IC16-56/160442 | Corrigendum No.1 for Supply,Installation and commissioning of GPU based High Performance Computing (HPC) Cluster. | 28-02-2017 upto 13.00 Hrs. | |
TFR/PD/F-730/IC16-56/160442 | Supply,Installation and commissioning of GPU based High Performance Computing (HPC) Cluster. | 28-02-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-619 /0034 | Corrigendum No. 1 for Supply, Installation, Commissioning of Cryogen free 5T-1T Vector magnet for STM with 4 inch room temperature bore and powersupply. | 09-02-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-616 /0031 | Corrigendum No. 1 for Supply, Installation and Commissioning of Cryogen-free Variable Temperature Insert (VTI) Cryostat System from 1.5k to room temperature with 9Tesla Magnet along option of Dilution fridge probe/insert with base temperature of 10-15mk. | 01-02-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-614 /0029 | Corrigendum No. 1 for Supply, Installation and Commissioning of Scanning Electron Microscope with accessories. | 24-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-619 /0034 | Supply, Installation, Commissioning of Cryogen free 5T-1T Vector magnet for STM with 4 inch room temperature bore and power supply. | 25-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-618 /0033 | Supply, Installation, Commissioning of Laser based Lithography tool with sub-micron feature resolution system. | 25-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-617 /0032 | Supply and Installation of 2 inch UHV Compatible Sputtering Sources with power supply/accessories. | 25-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-616 /0031 | Supply, Installation and Commissioning of Cryogen-free Variable Temperature Insert (VTI) Cryostat System from 1.5k to room temperature with 9Tesla Magnet along option of Dilution fridge probe/insert with base temperature of 10-15mk. | 25-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-615 /0030 | Supply, Installation, Commissioning of Field Flow Fractionation-Multi Angle Light Scattering and dynamic light scattering (FFF-MALS-DLS) system along with accessories. | 24-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-614 /0029 | Supply, Installation and Commissioning of Scanning Electron Microscope with accessories. | 24-01-2017 upto 13.00 Hrs. | |
TFR/PD/IC16-613 /0028 | Supply, Installation, Commissioning and Training for Confocal Microscope system with accessories. | 24-01-2017 upto 13.00 Hrs. | |
TFR/PD/16-17/CHS/0021 | Corrigendum No. 2 for Empanelment of Agencies/Contractors for Construction of Hanger Structure at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 29-12-2016 upto 13.00 Hrs. | |
TFR/PD/F-577/IC16-42/160343 | Supply, Installation and Commissioning of Live Cell Imaging Microscope at TIFR-TCIS Hyderabad. | 24-01-2017 upto 13.00 Hrs. | |
TFR/PD/16-17/CHS/0021 | Corrigendum No. 1 for Empanelment of Agencies/Contractors for Construction of Hanger Structure at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 22-12-2016 upto 13.00 Hrs. | |
TFR/PD/16-17/ICT/0022 | Corrigendum for Design, Supply, Installation and Commissioning of Active ICT Equipments for Campus Wide Wired and Wireless Networking at Fret-B Campus at Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 08-12-2016 upto 13.00 Hrs. | |
TFR/PD/16-17/ICT/0022 | Design, Supply, Installation and Commissioning of Active ICT Equipments for Campus Wide Wired and Wireless Networking at Fret-B Campus at Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad. | 08-12-2016 upto 13.00 Hrs. | |
TFR/PD/16-17/CHS/0021 | Empanelment of Agencies/Contractors for Construction of Hanger Structure at 36/P, Gopanpally Village, Serilingampally Mandal, Ranga Reddy District, Hyderabad | 07-12-2016 upto 13.00 Hrs. | |
TFR/PD/IC16-376/160222 | Tender Notice for Supply, Installation and Commissioning of Automated Microwave Peptide Synthesizer designed for FMOC Solid Phase Peptide Synthesis to TIFR-TCIS, Hyderabad | 06-12-2016 upto 13.00 Hrs | |
TFR/PD/16-17/IEW/160078 | Empanelment of agencies/contractors to undertake Internal Electrical works for newly constructed First Research Building at 36/P, Gopanpally Village, Seri Lingampally, Range Reddy District, Hyderabad. | 23-08-2016upto 13.00 Hrs. | |
TFR/PD/16-17/IF/160079 | Empanelment of agencies/contractors to undertake Interior Furnishing Works | 24-08-2016 upto 13.00 Hrs | |
TFR/PD/16-17/MF/160080 | Empanelment of Agencies/Contractors for Supply & Installation of Modular Furniture for newly constructed First Research Building at 36/P, Gopanpally | 25-08-2016 upto 13.00 Hrs | |
TFR/PD/WO15-539/150310/PUB | Corrigendum for Engagement of Clearing and Forwarding Agency for Customs | 15-02-2016 upto 13.00 Hrs. | |
TFR/PD/IC15-500/150286/PUB | Corrigendum for Supply, Installation, Calibration and Training of Flow | 01-02-2016 upto 13.00 Hrs | |
TFR/PD/WO15-539/150310/PUB | Engagement of Clearing and Forwarding Agency for Customs Clearance of | 10-02-2016 upto 13.00 Hrs | |
TFR/PD/WO15-538/150309/PUB | Providing Round the Clock Catering and Serving Services to TIFR-TCIS | 08-02-2016 upto 13.00 Hrs | |
TFR/PD/IC15-500/150286/PUB | Supply, Installation, Calibration and Training of Flow Cytometer to | 25-01-2016 upto 13.00 Hrs | |
TFR/PD/WO15-329/150207 | Providing Housekeeping Services to TIFR-TCIS Transit Campus, Students | 01-12-2015 upto 13.00 Hrs | |
TFR/PD/CA15-274/150156 | Corrigendum No. 2 for Supply, Installation, Configuration, Testing & | 17.11.2015 upto 13.00 Hrs. | |
TFR/PD/CA15-274/150156 | Corrigendum for Supply, Installation, Configuration, Testing & | 03.11.2015 upto 13.00 Hrs. | |
TFR/PD/CA15-274/150156 | Supply, Installation, Configuration, Testing & Demonstration for satisfactory Performance of High Performance Computing (HPC) Cluster at | 27.10.2015 upto 13.00 Hrs. | |
TFR/PD/WO15-275/150148 | Appointment of an Architect for Architecture Consultancy for Expeditious construction of prefab Laboratory Animal Facility for its upcoming TIFR-Hyderabad Campus, (Adjacent to Central University of Hyderabad, Gachibowli), Survey No. 36/P, Gopanpally Village,Serilingampally (Mandal), Ranga Reddy Dist., Hyderabad, Telangana. | 20-10-2015 | |
Corrigendum : Page No.11,Item No. 13,(in below tender for Security services PDF & DOC) - To be read as Average annual turnover during last 3 years ending 31st March of previous financial year | |||
TCIS/PCH/WO15-0096 | Tender for providing round the clock Security Services for transit campus at Narsingi, Gandipet road and its Permanent Campus at Gopanpally, Hyderabad | 09.07.2015 | PDF/ / DOC |
TCIS/PCH/CN14-0311 | Tender for Architectural Consultancy of prefab lab and animal facility at TIFR Hyderabad campus Gopanpally Plot B | 27.03.2015 | |
TCIS/PCH/IC14-0246/PUB | Tender for Surface Area analysis instrument | 27.02.2015 | |
TCIS/PCH/IC14-0267/PUB | Tender for High Performance (HR/AM) Bench Top Orbitrap / Ion trap system | 27.02.2015 | |
TCIS/PCH/IC14-0230/PUB | Tender for Scanning Electron Microscope with accessories | 27.02.2015 | |
TCIS/PCH/IC14-0229/PUB | Tender for CD Spectrometer with accessories for Powder CD and Automatic titration | 27.02.2015 | |
TCIS/PCH/IC14-0219/PUB | Tender for Micro Raman Spectrometer | 27.02.2015 | |
TCIS/PCH/IC14-0175 | Tender for High Pressure Helium Recovery Compressor | Due date revised to | |
TCIS/PCH/IC14-0156 | Tender for Dynamic Mechanical Analyser (DMA) | Due date revised to | |
PUB-001/2014 | Tender for Prefab Hostel Facility | Due date revised to | |
PUB-001/2014 | Tender for Prefab Hostel Facility | 08-04-2014 |